Full-life-cycle management system and method for nuclear power instrument

A technology with a full life cycle and management system, applied in the field of nuclear power engineering instrument control, can solve problems such as untimely information sharing, information transmission deviation, and affecting project quality, and achieve the effect of optimizing the construction process and improving collaborative efficiency

Active Publication Date: 2020-05-01
中广核工程有限公司 +3
View PDF3 Cites 1 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0005] In order to solve the technical problems of untimely information sharing and deviation in information transmission in the existing technology, which affect the quality of the project, the present invention proposes a full life cycle management system and method for nuclear power instruments

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Full-life-cycle management system and method for nuclear power instrument
  • Full-life-cycle management system and method for nuclear power instrument
  • Full-life-cycle management system and method for nuclear power instrument

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0025] An embodiment of the present invention provides a full life cycle management system for nuclear power instruments, such as figure 1 As shown, the system includes:

[0026] The design module 100 obtains the design parameters of nuclear power instruments, and changes the design parameters according to the actual situation, generates design technical specification parameters, installation parameters and debugging parameters according to the design parameters of nuclear power instruments, and generates design intermediate parameters at the same time; wherein, the design intermediate parameters Including design cost parameters and design progress parameters, the design cost parameters are used to characterize the proportion of the cost of the design module 100 in the actual cost of nuclear power meters; the design progress parameters are used to characterize the proportion of the production progress of the design module 100 in the actual progress of nuclear power meters; wher...

Embodiment 2

[0052] The present invention also provides a full life cycle management method for nuclear power instruments, which is applicable to a full life cycle management system for nuclear power instruments as in Embodiment 1, such as figure 1 As shown, the method includes:

[0053] Step S1, obtain the design parameters of the nuclear power instrument, and change the design parameters according to the actual situation, generate design technical specification parameters, installation parameters and debugging parameters according to the design parameters of the nuclear power instrument, and generate design intermediate parameters at the same time; wherein, the design intermediate parameters include Design cost parameters and design progress parameters, the design cost parameters are used to represent the proportion of the cost of the design process to the actual cost of nuclear power instruments; the design progress parameters are used to represent the proportion of the production progre...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a full-life-cycle management system and method for a nuclear power instrument. The system comprises a design module which obtains the design parameters of the nuclear power instrument, changes the design parameters according to the actual conditions, generates design technical specification parameters, installation parameters and debugging parameters according to the designparameters of the nuclear power instrument, and generates design intermediate parameters at the same time; the purchasing module is used for subpackaging and purchasing the nuclear power instrument according to the design technical specification parameters, generating purchasing information and generating purchasing intermediate parameters at the same time; the installation module is used for installing the nuclear power instrument according to installation parameters and the purchase information, generating installation state information and generating installation intermediate parameters; and the debugging module is used for debugging the nuclear power instrument according to the debugging parameters and the installation state information, generating debugging state information and generating debugging intermediate parameters at the same time. According to the invention, transparency of each link of design, purchase, installation and debugging of the nuclear power instrument is realized, and collaboration of each service department is realized.

Description

technical field [0001] The invention relates to the field of management and control of nuclear power engineering instruments, in particular to a full life cycle management system and method for nuclear power instruments. Background technique [0002] The development of nuclear power is of great significance to ensure my country's energy security, protect the environment, realize energy structure optimization and sustainable development, and improve my country's comprehensive economic strength and industrial technology level. The safe and efficient development of nuclear power is an important energy policy in my country. The business process of nuclear power engineering construction is mainly composed of engineering design (E), complete equipment (P), civil installation (C), commissioning and start-up (S) and project management (M). Through the exchange of physical objects and information, business logic interweaves among these professions, systems, and sectors, forming a com...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): G06F17/10G06F40/174G06Q10/06G06Q10/08G06Q50/06
CPCG06F17/10G06Q10/0631G06Q10/08G06Q50/06Y04S10/50
Inventor 胡乐杨秦秦龚邦新郭景任肖瑾黄文强刘金明田骏
Owner 中广核工程有限公司