A vertical water-stop structure and construction method for water conservancy projects
A vertical water stop and water conservancy engineering technology, applied in water conservancy projects, marine engineering, waterway systems, etc., can solve problems such as high maintenance costs and difficult maintenance, and achieve the effect of reducing maintenance costs and simple maintenance.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0043] Such as figure 1As shown, a vertical water-stop structure of a water conservancy project includes a dam body 1. The top wall of the dam body 1 is provided with installation grooves 11 along the vertical direction. At least two groups of installation grooves 11 are provided. . Each group includes a plurality of installation grooves 11 distributed at intervals along the length direction of the dam body 1 , and the installation grooves 11 of two adjacent groups are staggered. Each group of installation grooves 11 is collinear along the length direction of the dam body 1, and the distance between each group of adjacent two installation grooves 11 is less than the length of the installation grooves 11, and a waterproof compact layer 7 is arranged between two groups of adjacent installation grooves 11 , the waterproof dense layer 7 is connected with the end of the installation groove 11 to prevent water from leaking from the interval between the two installation grooves 11; ...
Embodiment 2
[0057] A vertical water stop construction method for water conservancy projects, comprising the following steps:
[0058] S1. Excavate the foundation pit, excavate the foundation pit on both sides of the roadbed facing the river according to the designed width, and lay waterproof piles around the foundation pit;
[0059] S2. Formwork production. According to the design, the dam body formwork and the installation groove formwork are produced;
[0060] S3. Formwork installation, install and fix the dam body formwork in the foundation pit, and then fix the installation groove formwork between the dam body formwork, set up two groups of installation groove formwork, each group is arranged at intervals along the length direction of the dam body 1, and the two The dislocation setting of the installation groove template of the group;
[0061] S4, pouring the dam body 1, pouring concrete in the formwork of the dam body 1;
[0062] S5, formwork removal, after the concrete is solidifi...