Small-section canal lining rapid construction method
A construction method and channel technology, applied in the field of infrastructure engineering, can solve the problems of difficult to guarantee construction quality, large formwork, multiple manpower, etc., and achieve the effect of improving construction progress and quality, improving construction quality and saving wood.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment
[0025] Embodiment: A kind of small cross-section canal lining fast construction method, comprises the following steps:
[0026] (1) Measurement stakeout:
[0027] Carry out measurement and stakeout according to the plane position of the drainage ditch provided by the design drawings, use a total station or theodolite to define the central positioning pile and the bottom slope junction pile, and place the central pile at every 50m interval (nail piles at intervals of 5m at the bend) and number them , use a level to measure the height of the pile point, and then determine the sideline of the drainage ditch according to the center line, and mark it with a lime line;
[0028] (2) Channel filling
[0029] The channel is filled with the excavated earthwork in the nearest grid, paved and filled according to the horizontal layer, the layer thickness and compaction parameters are determined according to the field test; the filled soil material is mainly transported by loader and backh...
PUM

Abstract
Description
Claims
Application Information

- R&D
- Intellectual Property
- Life Sciences
- Materials
- Tech Scout
- Unparalleled Data Quality
- Higher Quality Content
- 60% Fewer Hallucinations
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2025 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com