Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

Construction method for super large pile distance deep foundation pit supporting system

A technology of deep foundation pit support and construction method is applied in the construction field of deep foundation pit support system with super large pile spacing, which can solve the problems of large environmental risk of foundation pit support, high cost of pile support system, disturbance of base soil, etc. Achieve good social and economic benefits, convenient construction, and increase the effect of horizontal stiffness

Inactive Publication Date: 2020-07-17
POWERCHINA XIBEI ENG
View PDF4 Cites 1 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

The pile support system is expensive and has a long construction period, while the pile anchor system is easy to disturb the base soil during the construction process. When the soft soil layer is thick, in order to meet the designed uplift bearing capacity, the anchorage section needs to penetrate the soft soil layer. Therefore, it causes a greater environmental risk and a lot of waste in the foundation pit support

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method for super large pile distance deep foundation pit supporting system
  • Construction method for super large pile distance deep foundation pit supporting system
  • Construction method for super large pile distance deep foundation pit supporting system

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0040] In order to realize pile row support with large pile spacing under unfavorable engineering geological conditions such as the presence of sand layers, this embodiment provides a construction method for a deep foundation pit support system with super large pile spacing, and the construction is carried out at equal intervals along the length direction of the foundation pit. Two rows of support piles 1, when there is an existing structure 2 at the construction site of the support pile 1, construct the support pile 1 after crossing the existing structure 2, and construct the crown on the top of the support pile 1 after the construction of the support pile 1 Beam 5, and then construct slab wall 4 between the support piles 1 on both sides of the existing structure 2, wherein the slab wall 4 is constructed by the reverse method, and the support system is constructed after the slab wall 4 is completed.

[0041] The present invention is applicable to the foundation pit engineering...

Embodiment 2

[0043] This embodiment provides a construction method for a deep foundation pit support system with super large pile spacing. Two rows of support piles 1 are constructed at equal intervals along the length direction of the foundation pit. When there are existing structures 2 at the construction site of the support piles 1 After crossing the existing structure 2, the support pile 1 is constructed. After the construction of the support pile 1, the crown beam 5 is constructed on the top of the support pile 1, and then the slab wall is constructed between the support pile 1 on both sides of the existing structure 2. 4. Among them, the board wall 4 is constructed by the reverse method, and the support system is constructed after the board wall 4 is completed.

[0044] The distance between the support piles 1 and the construction of equal intervals is not greater than twice the diameter of the support piles 1, and the distance between the support piles 1 on both sides of the existing...

Embodiment 3

[0047] On the basis of Embodiment 1, this embodiment provides a construction method for a deep foundation pit support system with super large pile spacing, which specifically includes the following steps:

[0048] Step 1) construction of the support pile 1, when encountering the existing structure 2, the construction of the support pile 1 is carried out across the existing structure 2;

[0049] Step 2) After the construction of the support pile 1 is completed, the crown beam 5 is constructed;

[0050] Step 3) Carry out earthwork excavation layer by layer at the setting position of the slab wall 4, expose the support pile 1, lower the reinforcement model of the slab wall 10 on the first layer, and connect the support pile 1 and the crown beam 5 to the first layer slab respectively Wall 10 reinforcement connection; such as figure 1 shown;

[0051] Step 4) Casting the first layer of slab wall 10 from top to bottom between the two retaining piles 1, using wooden formwork 12 as t...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention provides a construction method for a super large pile distance deep foundation pit supporting system. Two rows of supporting piles are constructed at equal distances in the length direction of a foundation pit; when an existing structure exists at the construction part of the supporting piles, the supporting piles are constructed after crossing of the existing structure; after the supporting piles are constructed, crown beams are constructed at the tops of the supporting piles, and then board walls are constructed between the supporting piles located on the two sides of the existing structure, wherein the board walls are constructed with a reverse method; and after the board walls are constructed, the supporting system is constructed. The distance of the equal distance construction of the supporting piles is not larger than two times the diameter of the supporting piles, and the distance between the supporting piles on the two sides of the existing structure is larger than two times the diameter of the supporting piles. Compared with the prior art, row pile supporting and the reverse building method construction are combined, the advantages of the row pile supportingand the reverse building method construction are fully utilized, the structure is simple, safety and reliability are achieved, construction is convenient, and the manufacturing cost is low. Meanwhile,no anchor rope is used, an existing building and existing pipelines are protected while the foundation pit is protected, and good application prospects in foundation pit supporting in the fields suchas city municipal administration are achieved.

Description

technical field [0001] The invention belongs to the technical field of municipal infrastructure, and in particular relates to a construction method for a deep foundation pit support system with super large pile spacing. Background technique [0002] With the rapid development of my country's economy, the scale of ground buildings is getting larger and larger, and at the same time, the underground space is deeply developed, and the requirements for foundation pit engineering are also increasing, and the safety and stability of deep foundation pit support are becoming more and more complicated. Deep foundation pit engineering is a temporary project, and its technical complexity is much higher than that of permanent foundation construction [0003] In the process of excavating deep foundation pits, in order to ensure the safety and reliability of deep foundation pits and prevent casualties and property losses caused by the collapse of deep foundation pits, it is often necessary...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E02D17/04
CPCE02D17/04
Inventor 吕佼佼高徐军张友科刘园苏国省柳兴旺白鹤甘鹏山秦青阳韩文斌贾彦武查亚辉俱军涛马高峰
Owner POWERCHINA XIBEI ENG
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products