Dam concrete pre-stressed anchor cable blasting demolition sampling method

A technology of prestressed anchor cables and concrete, applied in the direction of sampling devices, etc., can solve the problems of unclear stress corrosion mechanism of prestressed anchor cables, and achieve the effects of saving mechanical equipment, simple process flow and safe process

Active Publication Date: 2020-08-14
SINOHYDRO BUREAU 16 CO LTD
View PDF8 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0006] At present, the research content of prestressed anchor cables is still limited to the change law of prestressed anchor cables, the cause of failure and the influencing factors. The stress corrosion mechanism of prestressed anchor cables is still unclear, and the research on the durability of anchor cables is still in its infancy.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Dam concrete pre-stressed anchor cable blasting demolition sampling method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0025] The present invention will be described in detail below in conjunction with the drawings. The enumerated embodiments can enable those skilled in the art to better understand the present invention, but do not limit the present invention in any form.

[0026] Such as figure 1 As shown, a dam concrete prestressed anchor cable demolition sampling method is mainly aimed at the current hydraulic dam 1, which is demolished by blasting from top to bottom and layer by layer downward. The removal method is:

[0027] 1.1) Before the demolition of the whole concrete blasting, use the breaking hammer to break the anchor pier, remove the internal tension of the anchor cable naturally, check the shrinkage of the anchor cable, and evaluate the internal residual tension to guide the subsequent demolition of the anchor cable; before the demolition of the whole concrete blasting , first measure the length of the exposed end of the anchor cable, as an important reference for subsequent me...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a dam concrete pre-stressed anchor cable demolition sampling method, which is characterized in that blasting demolition is conducted downwards layer by layer from top to bottom, and blasting holes should keep away from the position of an anchor cable. The demolition method comprises the steps of before integral concrete blasting demolition, breaking an anchor cable pier byusing a breaking hammer, naturally relieving internal tension of the anchor cable, and conducting fixed-point marking on the horizontal position of the sampling anchor cable before blasting demolition; performing safety protection on the surface of the dam body before blasting; performing accurate blasting and deslagging operation; breaking the residual concrete of the sampling anchor cable pier by using the breaking hammer, and transferring and storing the sampling anchor cable after the sampling anchor cable is completely cleaned out. The technological process is simple, rapid and convenient, mechanical equipment is saved, the technology is safe, various properties of the anchor cable are not affected, and an objective sample is provided for anchor cable research. The sampling anchor cable is subjected to a research experiment, analysis and research are conducted according to macroscopic inspection and mechanical property test results of the anchor cable, related research parametersare obtained, and thus safety evaluation and service life prediction of the anchor cable are conducted.

Description

technical field [0001] The invention belongs to construction technology for buildings, in particular to a sampling method for removing prestressed anchor cables in hydropower projects. Background technique [0002] Prestressed anchor cable is a construction technology that embeds steel strands into large buildings or rock formations for prestressing, and transfers the support stress of the main structure to the deep active support method. A structure anchored by the structure can more effectively bear the tensile and shear forces generated by the load, and the transmission depth of these forces is much greater than that of an unanchored structure. [0003] A typical example of the successful application of prestressed anchor cables to large-scale hydraulic structures in the world is the heightening and strengthening project of the Sherfa Dam in Algeria in the 1930s. Since then, more and more hydraulic structures have applied prestressed anchor cable technology. [0004] Th...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): G01N1/04
CPCG01N1/04
Inventor 罗志敏陈祖荣蒋亨强朱晓秦孟继慧刘振宇赖建文罗瑞池国彪林立胡豹
Owner SINOHYDRO BUREAU 16 CO LTD