The present application relates to the technical field of municipal underground passage construction, and particularly relates to a municipal underground passage construction method for passing under a railway, steps S1, measuring and
lofting are performed on both sides of the railway to determine the position of the foundation pit, step S2, a support column is constructed on the retaining
pile on the side of the foundation pit close to the railway foundation, a support beam is arranged below the railway, step S3, grooving is simultaneously performed on the side of the foundation pit close to the railway on both sides, after the grooving, the positioning beam and the guide beam are poured and positioned by taking the inner wall of the soil groove as a formwork, step S4, after the excavation reaches the corresponding
pipe cover elevation above the to-be-excavated underground passage, a jacking device is installed, and the
pipe cover is jacked after a
insertion hole is drilled on the retaining
pile; step S5, the two sides of the steel
sheet pile are synchronously excavated by the excavation equipment, and the
pipe cover on both sides and below the to-be-excavated underground passage is jacked according to the excavation progress; the support column and the support beam are arranged on both sides of the railway, forming an
active support system for the railway foundation, and effectively controlling the settlement and deformation of the railway foundation.