Tower crane dismantling method
A technology of tower crane and jib, applied in the directions of crane, transportation and packaging, can solve the problems of low applicability and complex structure, and achieve the effect of improving work efficiency
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment
[0024] Example: refer to Figure 1-4 , a tower crane removal method, comprising the following steps:
[0025] S1. Removal of the balance weight: fix the lifting trolley on the root of the balance arm 1, lift and disassemble the balance weight with the help of a crane using a wire rope, first remove the connecting plate installed on the balance weight, and then follow the reverse order of the counterweight, in order Remove the balance weight;
[0026] Among them, the width between the connecting plates is determined according to the size of the pulley, and the bushing in the middle is fixed with M16 bolts, and the bolt length is reserved for 100mm;
[0027] S2. Removal of the boom 7: lift the boom 7 to be dismantled, then remove the two lower pins, replace the original pins with two M16X150 bolts, and then pull out the upper chord pins, and use them under the load of the wire rope to make the The boom 7 to be disassembled slowly descends and hangs it on the two pin shafts of ...