Tunnel waterproof plate construction dotting device and dotting method thereof

A tunnel waterproof board and apex technology, which is applied in tunnels, tunnel linings, shaft equipment, etc., can solve problems such as unstable installation of waterproof boards, waste of materials, and inability to uniformly standardize hot-melt gaskets, so as to improve construction efficiency and construction quality. The effect of reducing consumption and stabilizing the installation

Pending Publication Date: 2021-02-19
CHINA RAILWAY NO 2 ENG GRP CO LTD +1
View PDF0 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0005] The purpose of the present invention is to solve the problems in the prior art that the arrangement of hot-melt gaskets is controlled by construction personnel based on experience, and the arrangement of hot-melt gaskets cannot be uniformly standardized, resulting in unstable installation of the waterproof board, or a piece of waterproof The board is fixed with too many hot-melt gaskets, resulting in a technical problem of waste of materials. A construction dotting device and a dotting method for tunnel waterproof boards are provided

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Tunnel waterproof plate construction dotting device and dotting method thereof
  • Tunnel waterproof plate construction dotting device and dotting method thereof
  • Tunnel waterproof plate construction dotting device and dotting method thereof

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0042] Such as figure 1 , figure 2 and Figure 5 As shown, in this embodiment, a dotting device for tunnel waterproofing construction includes a frame body 1 on which several positioning pieces 2 are arranged, and the positioning pieces 2 are used to mark the dotting positions.

[0043] Specifically, the number of the positioning parts 2 is three, and the three positioning parts 2 are arranged in the shape of an isosceles triangle. The structure of the waterproof board in the existing design is a rectangular plate. By setting three positioning parts 2, three The positioning part 2 is surrounded to form an isosceles triangle, and after one dotting, three dotted positions can be formed on the rock wall, and the three dotted positions form an isosceles triangle, and then the frame body 1 is rotated 180° around one of the dotted positions as the base point , carry out the second dotting, and form five dotting positions on the rock wall, and the five dotting positions are mispla...

Embodiment 2

[0049] Such as Figure 1-Figure 5 As shown, in this embodiment, the difference with Embodiment 1 is that a marking pen 3 is respectively provided in each of the positioning holes 21, which is convenient for directly performing a dotting operation at the position of the positioning hole 12 through the marking pen 3, and does not need Temporary search for dotting tools to improve construction efficiency.

[0050] Further, the frame body 1 is provided with moving parts, and the moving parts are used to resist the marker pens 3, and push the three marker pens 3 at the same time through the moving parts, so that the three marker pens 3 can be placed on the rock wall at the same time. Firstly, the construction efficiency is improved, and secondly, compared with the three marking pens 3, it has an advantage in sequentially marking at the same time: in the process of sequentially marking, the frame body 1 held by the construction personnel may be displaced on the rock wall or due to t...

Embodiment 3

[0055] In this embodiment, a tunnel waterproof board construction marking method using a tunnel waterproof board construction marking device as described in Embodiment 1 or 2, the steps include:

[0056] Step 1, install the frame body: place the frame body 1 on the rock wall;

[0057] Step 2, dotting for the first time: perform dotting operation on the positions of the three positioning pieces 2 arranged in an isosceles triangle, and form three dots on the rock wall;

[0058] Step 3, rotating the frame body: rotate the frame body 1 around one of the positioning parts by 180°;

[0059] Step 4, dotting for the second time: perform dotting operation on the positions of the other two positioning parts 2 whose positions have changed, and form five dots on the rock wall.

[0060] The present invention relates to a tunnel waterproof board construction dotting method. Three positioning pieces 2 are arranged on the frame body 1, and the three positioning pieces 2 are surrounded to for...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention relates to the technical field of tunnels and underground engineering, in particular to a tunnel waterproof plate construction dotting device and a dotting method thereof. The tunnel waterproof plate construction dotting device comprises a frame body, the frame body is provided with a plurality of positioning pieces, and the positioning pieces are used for identifying dotting positions. The number of the positioning pieces and the shape formed by the positioning pieces can be customized according to needs, so that after waterproof plates are welded through hot melting gaskets atthe dotting positions, the looseness of the waterproof plates can be improved, the welding stability of the waterproof plates is improved, the consumption of the hot melting gaskets can be reduced, and the waterproof plates can be stably mounted by using the least hot melting gaskets; and the utilization rate of the hot melting gaskets is improved, artificial sensory judgment does not need to be doped in the construction process, the distance between the dotting positions does not need to be measured, so that the relative mounting positions between the hot melting gaskets are more accurate, the mounting of the waterproof plates is unified and standardized, and the construction efficiency and the construction quality are improved.

Description

technical field [0001] The invention relates to the technical field of tunnels and underground engineering, in particular to a tunnel waterproof board construction marking device and a marking method thereof. Background technique [0002] Tunnel waterproofing and drainage is a particularly important construction link in tunnel construction. The steps of traditional waterproofing and drainage construction include: construction of geotextiles and circumferential blind pipes, fixing hot-melt gaskets and welding waterproof boards and hot-melt gaskets. The installation of waterproof boards The quality depends on the arrangement quantity and arrangement shape of the hot-melt gasket. [0003] In the prior art, the arrangement of hot-melt gaskets is usually arranged by workers based on experience. The number of hot-melt gaskets corresponding to each waterproof board and the arrangement and shape of these number of hot-melt gaskets are not unified, resulting in the unevenness of the ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): E21D11/38
CPCE21D11/381
Inventor 龚学亮董兵袁枫杰李元亿杜攀阳东廷王昊乾刘畅
Owner CHINA RAILWAY NO 2 ENG GRP CO LTD