A construction method and platform wall technology, applied in artificial islands, water conservancy projects, infrastructure projects, etc., can solve the problems of existing subgrade settlement, large amount of earth excavation, and high construction costs, and reduce structural technical risks and construction risks. , Avoid the effect of large foundation excavation and shorten the construction period
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0022] like figure 1 As shown, the construction method of the cast-in-place platform wall with multi-point tenons includes the existing hardened ground 1, which is located within the base plate of the platform wall. The first step: roughen the hardened ground 1. When roughening, pull The texturer leans against the template and proceeds along the direction of the transverse slope. During one process, do not stop in the middle, so that the texture of the napping is smooth, and the depth of the napping is 1~2mm;
[0023] Step 2: According to the on-site stakeout, drill a positioning hole 2 with a diameter of 100mm on the original concrete floor. The position of the positioning hole 2 can be adjusted according to the actual situation of the road surface. Choose a place with less ground damage. The drilling depth is 200mm, ensuring There are only two circular holes per linear meter along the route, at least two positioning circular holes 2 per linear meter, and the distance between...