Embodiment 1
[0048] like figure 1 As shown, Embodiment 1 of the present disclosure provides a joint inspection method for substations, specifically, including a method for linkage between the joint inspection system and the main and auxiliary equipment monitoring system, and the specific functions are:
[0049] Step 1-1: The main and auxiliary equipment monitoring system sends the main and auxiliary equipment linkage signal to the inspection processing system through the network security protection equipment.
[0050] Step 1-2: The joint inspection service in the inspection processing system finds the associated physical object ID and equipment point list according to the main equipment code of the linkage signal.
[0051] Step 1-3: The joint inspection service obtains the associated linkage policy list from the linkage policy configuration according to the device point list.
[0052] Steps 1-4: The joint inspection service judges whether the linkage policy list is empty.
[0053] If the...
Embodiment 2
[0101] like image 3 As shown, Embodiment 2 of the present disclosure provides a substation joint inspection system, including:
[0102] The inspection processing system is deployed in the substation. The inspection processing system communicates with the superior system. The inspection processing system is connected to the robot and the detection device through the security access layer. The inspection processing system is also connected to multiple optical acquisition devices through video collection, storage and forwarding equipment; the main and auxiliary The equipment linkage signal is sent to the inspection processing system through the network security protection equipment; the environmental monitoring system is connected to the inspection processing system through the security access layer;
[0103] Several optical acquisition devices include fixed-mounted visible light gun camera (bullet network camera for short), visible light dome camera (spherical network camera fo...
Embodiment 3
[0133] like Figure 7 As shown, Embodiment 3 of the present disclosure provides a substation joint patrol inspection early warning review method, including the following steps:
[0134] Step 3-1: The user controls the substation equipment inspection task through the user interface control of the inspection processing system or the joint inspection service timing control. The inspection task includes the inspection task code, the inspection task name, and the substation equipment points that need to be inspected Bit list, inspection task priority, inspection task timing period, inspection task creator, inspection task creation time.
[0135] Step 3-2: The joint inspection service performs task scheduling.
[0136] Step 3-2-1: The joint inspection service finds the associated optical acquisition device list and inspection robot list according to the equipment point list in the inspection task.
[0137] Step 3-2-2: The joint inspection service combines the task status of the op...