Manual hole digging pile quicksand layer protection device and construction method thereof

A technology of manual excavation piles and protection devices, which is applied in excavation, sheet pile walls, foundation structure engineering, etc. It can solve the problems of difficult alignment of bolt connections, affecting the quality of pile foundations, and difficult fixing of steel casings, so as to simplify construction The effect of difficulty, simple structure and low cost

Pending Publication Date: 2021-03-16
CHINA RAILWAY SHANGHAI ENGINEERING BUREAU GROUP CO LTD +1
View PDF0 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] The construction is simple by using straw to add steel bars and wooden planks to block sand. However, after the straw rots, a cavity will be formed, which will affect the quality of the pile foundation. Traditionally pressed into the rigid casing, using the original concrete support and hydraulic jacking, the process is complicated, due to the narrow space in the hole. , the construction is difficult, the use of steel casing still has the effect of reducing drag on the pile foundation, and affects the load of the pile foundation itself
The traditional steel casing is cylindrical and divided into 2-4 pieces. The upper and lower sides of each piece are connected by bolts. There are disadvantages such as difficulty in aligning the upper and lower bolt connections, difficult fixing of the steel casing, and poor water-stop effect.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Manual hole digging pile quicksand layer protection device and construction method thereof
  • Manual hole digging pile quicksand layer protection device and construction method thereof

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0015] A protective device for quicksand layers of manual excavated piles, which is composed of several conical steel casings 1 tightly socketed in the form of tiles. Trapezoidal.

[0016] Further, a rubber ring 2 is arranged between the upper and lower tapered steel casings, the rubber ring 2 is conical in shape, consistent with the tapered steel casings, and can realize the watertight seal of the upper and lower tapered steel casings.

[0017] Further, the tapered steel casing 1 is rolled from fan-shaped steel plates, and the joints on both sides of the fan-shaped steel plates are welded inward to a steel edge 3 with a width of 8-15 cm, and holes are drilled on the steel edge 3 for installing bolts.

[0018] Further, the upper diameter of the tapered steel casing is 10-20cm smaller than the pile diameter, the lower diameter is 20-30cm larger than the pile diameter, and the casing is 20-40cm high.

[0019] Further, there are 3-6 conical steel casings 1 (conditions for being ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention belongs to a manual hole digging pile quicksand layer protection device and a construction method thereof, and relates to building pile foundation construction. The manual hole digging pile quicksand layer protection device is formed by tightly sleeving a plurality of conical steel casings in a tile mode, the conical steel casings are arranged in a big-end-down mode, and the sectionsof the combined casings are trapezoidal. The construction method comprises the following steps that (1) the conical steel casings are prefabricated; (2) the position of a quicksand layer is detected;(3) double-liquid slurry is injected into the quicksand layer in an inclined downward mode; (4) manual downward excavation is conducted, and the first sections of conical steel casings are installed;(5) the double-liquid slurry is injected; (6) manual excavation is conducted, and the second sections of conical steel casings are installed; (7) the steps (3)-(6) are repeated until passing throughthe quicksand layer; (8) grouting and joint filling are conducted, and gaps between the steel casings and the quicksand layer are filled; (9) digging continues to be conducted downwards to the bottom,and a lower concrete retaining wall is poured in situ. According to the device and the construction method, the quicksand layer can be penetrated, the construction difficulty that a manual hole digging pile penetrates through the quicksand layer can be effectively simplified, and the construction efficiency is improved.

Description

technical field [0001] The invention belongs to a quicksand layer protection device and a construction method of an artificial hole-digging pile, and relates to the construction of building pile foundations. Background technique [0002] Existing manual hole-digging piles pass through the silt layer, use straw to add steel bars, planks to block the sand, and then use concrete to protect the wall. Another kind of steel casing construction adopts the quicksand layer when digging the hole. Generally, a steel casing casing with a height of 1-2m and a thickness of 4-5mm can be set in the well hole. The diameter is slightly smaller than the inner diameter of the concrete retaining wall, and the concrete support is used as a fulcrum. Use a small hydraulic jack to gradually press the steel casing into the soil to stop the quicksand. The steel casings can be sunk one by one, pressed into a section, excavated a section of pile holes until passing through the quicksand layer 0.5-1.0m,...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): E02D5/38E02D5/66E02D15/04E02D5/48E02D17/08E02D5/68
CPCE02D5/38E02D5/48E02D5/66E02D5/68E02D15/04E02D17/08
Inventor 左回刚陈建国周洪光户少勇周俊杰
Owner CHINA RAILWAY SHANGHAI ENGINEERING BUREAU GROUP CO LTD