Large-volume steel net rack integral lifting device and construction method
A technology of overall lifting and construction method, applied in the direction of lifting equipment braking device, hoisting device, transportation and packaging, etc., can solve the problems of reduced overall stability of the grid frame, difficult disassembly of the lifting bracket, and increased installation space. The effect of reducing the lifting control factor, reducing the reserved installation space, and high disassembly efficiency
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0031] Such as Figure 1-3 As shown, a large-volume steel grid overall lifting device, including the side support structure column 1 established on the ground surface, the middle support structure column 2 and the grid frame 3 to be lifted spliced on the ground, the grid frame 3 is reserved with edge The installation space of the support structure column 1 and the middle support structure column 2, the outer side of the side support structure column 1 is provided with a lifting support column 4, and a lifting beam frame 5 is supported and installed between the mutually symmetrical side lifting support columns 4, A hydraulic lifter 6 is installed on the lifting beam frame 5, and one end of the hydraulic lifter 6 is connected to a steel strand 7 and the steel strand 7 is connected to a preset lifting point provided at the lower chord of the grid frame 3, and the lifting support column 4 A chain hoist 8 is installed close to one side of the grid 3 , and the chain hoist 8 is con...
Embodiment 2
[0036] A construction method for the overall lifting of a large-volume steel grid structure, comprising the following steps:
[0037] 1) According to the design requirements, determine the positions of the side support structure column 1 and the middle support structure column 2 and install them on the ground. splicing and assembling into a whole, the grid 3 reserves space at the positions of the side support structure column 1 and the middle support structure column 2, and determines the initial offset of the X-axis and the Y-axis;
[0038] 2) According to the design position, the lifting support column 4 is installed on the outside of the side support structure column 1, and the lifting beam frame 5 is supported and installed on the top of the two symmetrical lifting support columns 4;
[0039] 3) Load-bearing frame 9 is installed on the top of middle support structure column 2, and the bottom of load-bearing frame 9 and lifting beam frame 5 is supported and installed;
[0...