Construction ventilation method for parallel three-hole method tunnel press-in type ventilation
A ventilation method and parallel tunnel technology, applied in mine/tunnel ventilation, earthwork drilling, mining installations, etc., can solve the problems of long smoke exhaust time, incomplete tunnel drainage, and difficult ventilation.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0022]Referfigure 1 A construction ventilation method of parallel three-way method, including parallel tunnels, three parallel tunnels, parallel tunnels, parallel tunnels, 1, left-line, positive cave 2, and right shifts 3, left lines 2 and the right thread positive hole 3 is located on both sides of the parallel guiding 1, and the adjacent tunnel is provided with a transverse channel 4; the parallel cavity 1 uses the TBM method superior, and the left passage 4 increases the left The excavation work surface of the line front hole 2 and the right shift of the right shift 3, the auxiliary left-line positive hole 2, the right shift is 3 construction.
[0023]Its section design must meet the dimensional requirements of the two-way driving and arrangement of two dumles 6, by increasing the cross-channel excavation work surface, and the transverse channel 4 should meet at least the single-way driving and the size of the wind tube 6.
Embodiment 2
[0025]Based on the first embodiment, the present invention employs a press-in ventilation, a ventilated fan 5 using an axial flow fan 5.
[0026]Further, the parallel guide hole 1, the left-line positive hole 2 and the right line positive hole 3 are provided with a shaft fan 5, and the axial flow fan 5 is connected to the corresponding tunnel facade, in the air tube. At the end of the end, there is a winding and wind speed detector 9 for real-time monitoring of the air supply, according to the air environment and working conditions of the cave, dynamically adjust the wind and air volume of the axial flow fan 5, and meet the needs of the palm sides. .
[0027]Further, the left-line positive hole 2 and the right-line positive hole 3 use the segmented tunnel construction, the left-line positive hole 2 and the right line positive hole 3 via the transverse passage 4 and the parallel guide hole 1, through parallel Cave 1 horizontal channel increases the auxiliary work surface of both sides, fro...
Embodiment 3
[0031]referencefigure 1 withfigure 2In the basis of Example 1 or 2, it is further, and at least two axial flow blower 5 in the parallel guideline 1, one of the axial flow blower 5 connects the wind tube 6 to left-line positive hole 2 auxiliary operation The secondary fan of TBM in parallel in parallel, and another axial fan 5 connects the duct 6 to the right shift of the air.
[0032]Further, the two axial flow blower 5 is connected to the wind tube 6 left and right, the left wind tube leads to the branch of the left-line positive hole 2 through the damper 7, the right wind tube is directed to the door 7 The branch duct of the right-line positive hole 3; one of the ends of the wind tube 6 and the two branch duct ends are provided with air volume and wind speed detector 9.
[0033]Further, the parallel guides 1, the left-line positive hole 2, and the wind tube 6 of the right line positive hole 3 is provided at the upper arched position of the tunnel.
[0034]Further, the transverse passage 4 ...