Industrial brick cutting equipment
A kind of cutting equipment and industrial technology, which is applied in the field of industrial brick cutting equipment, can solve the problems of time-consuming, time-consuming and labor-intensive processes, and achieve the effect of saving time and manpower
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0032] An industrial brick cutting equipment such as Figure 1-4 As shown, it includes a support frame 1, a first pressing rod 2, a first slider 3, a first support rod 4, a cutting blade 5, a transmission assembly 6 and a first clamping assembly 7, and the upper rear side of the support frame 1 slides is connected with the first pressing rod 2, the left and right sides of the upper part of the support frame 1 are slidably connected with the first slider 3, the first slider 3 on both sides is connected with the first support rod 4, and the first support rod 4 A cutting blade 5 is connected to the front side of the lower part, a transmission assembly 6 is provided on the upper front connection block of the support frame 1, and a first clamping assembly 7 is slidably connected to the lower front side of the transmission assembly 6.
[0033] The transmission assembly 6 includes a slide bar 61, a second support bar 62 and a first spring 63. The outside of the first slider 3 on both...
Embodiment 2
[0037] On the basis of Example 1, such as Figure 5 As shown, a charging assembly 8 is also included. The charging assembly 8 includes a third chute 81, a second limit rod 82, a third spring 83, a charging frame 84 and a screen 85. The lower part of the support frame 1 acts as two Both sides are connected with a third chute 81, the top of the third chute 81 on both sides is connected with a second limit rod 82, and the upper part of the third chute 81 on both sides is slidably connected with a charging frame 84. A screen 85 is arranged inside the material frame 84 , and a third spring 83 is connected between the material frame 84 and the third chute 81 on both sides.
[0038] When the bricks are cut, the bricks are manually placed on the screen 85 for collection, and then wait for the bricks to be air-dried, and the charging frame 84 moves downward under the action of gravity, and the charging frame 84 moves downward on both sides The third spring 83 is stretched, and after t...
Embodiment 3
[0040] On the basis of Example 2, such as Figure 6 As shown, a second clamping assembly 9 is also included, and the second clamping assembly 9 includes a pressure plate 91, a fourth spring 92 and a second pressing rod 93, and the upper front side of the cutting blade 5 is connected with a second pressing rod 93 , the pressure plate 91 is slidably connected to the left and right sides of the second lower pressing rod 93 , and the fourth spring 92 is connected between the pressure plate 91 on both sides and the second lower pressing rod 93 .
[0041] When the cutting blade 5 moves downward, the cutting blade 5 moves downward to drive the second pressing rod 93 to move downward, and the second pressing rod 93 moves downward to drive the pressure plates 91 on both sides through the fourth spring 92 on both sides. Moving downward, the pressure plates 91 on both sides move downward to drive the clamping frame 71 to move downward, so that there is no need to manually press down the ...