Blasting construction method for mine slope repair
A construction method and mine technology, applied in the field of mine slope management, can solve the problems of heavy mechanical trimming, poor slope forming effect, high cost of construction machinery, etc., to achieve the effect of reducing workload and ensuring integrity
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment
[0060] Such as Figure 1-Figure 3 Shown, a kind of mine slope restoration blasting construction method, described construction method comprises the following steps:
[0061] S1. Draw the drawings of the finished mine slope; the finished mine slope is stepped from top to bottom as the upper finished platform, the finished side slope, and the lower finished platform; the connection between the upper finished platform and the finished side slope is the top line, The connection between the slope and the lower end platform is the toe line;
[0062] S2. According to the final mine slope drawing, mark the position of each blasthole on the surface of the working face, and the blastholes are relatively located on the top of the upper finishing platform, the finishing side slope, the toe line and the lower finishing platform; by marking at the toe line The blast hole can ensure the integrity of the back slope to a great extent and reduce the workload of mechanical trimming in the later...