Job shop scheduling risk optimization method based on machine speed scaling
A technology of machine speed and scheduling risk, applied in instruments, calculation models, forecasting, etc., can solve problems such as high risk levels, poor performance indicators of scheduling schemes, and difficulty in meeting the actual requirements of job shop scheduling, achieving reduced delay and low scheduling. effect of risk
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0077] The embodiments of the present invention will be described in detail below. It should be noted that the embodiments are illustrative, not restrictive, and cannot limit the protection scope of the present invention.
[0078] The raw materials used in the present invention, unless otherwise specified, are conventional commercially available products; the methods used in the present invention, unless otherwise specified, are conventional methods in the art.
[0079] A risk optimization method for job shop scheduling based on machine speed scaling, the steps are as follows:
[0080] Step 1, set scheduling problem information:
[0081] Step 1.1, set the number of machines as m, the number of workpieces as n, and each workpiece contains o processes in is the i-th process of the j-th workpiece, which is in the equipment is processed on , the basic processing time is
[0082] Step 1.2, set the equipment failure rate to λ 0 , the expected downtime is β 0 , the optiona...