Temporary supporting structure on upper portion of steel bar truss floor support plate and construction method of temporary supporting structure
A technology of temporary support and steel truss, which is applied to the construction of buildings, pillars, and the preparation of building components on site. It can solve the problems of inconsistent reinforcement and thickness, long installation and disassembly time, waste of steel bars, etc., and achieve engineering volume. Small size, simple construction, wide range of trial scenarios
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0045] Embodiment one sees Figure 1-6 As shown, a temporary support structure for the upper part of a reinforced truss floor deck includes a reinforced truss floor deck, a structural beam 1, a temporary support composite frame and a temporary support. The reinforced truss floor deck includes a bottom supporting plate 2 and A group of floor deck steel bars 3 arranged along the longitudinal length of the bottom supporting plate 2 and arranged at intervals along the transverse direction.
[0046] The bottoms at both ends of the reinforced truss floor deck are respectively lapped on the structural beams 1 on both sides, and the temporary supports are arranged in two rows at intervals along the length direction of the structural beams 1, and the two rows of temporary supports are arranged in pairs and respectively Placed and fixedly connected on the upper side of the structural beams 1 on both sides, the temporary supporting composite frame is located above the steel truss floor d...
Embodiment 2
[0058] Example 2 Participation Figure 7 As shown, when the span of the floor deck is large, the temporary support can be a combination of a temporary support mother frame 4 and two temporary support sub-frames 5, wherein the temporary support mother frame is located in the middle, and the temporary support sub-frames are located on both sides. The way of connection is the same as that of Embodiment 1.
Embodiment 3
[0059] Example 3 Participation Figure 8 As shown, the difference from the first embodiment is that when the form of the steel truss is different, the temporary support of the steel truss floor deck of the present invention can still be used, and the support method is the same as the above-mentioned method.