Ship deck crane steel wire rope installation process method

A ship deck and installation process technology, applied in the direction of hoisting device, clockwork mechanism, etc., can solve the problems of installing the main steel wire rope, the gantry crane does not meet the lifting requirements, the main steel wire rope is heavy, and achieves the effect of solving the difficulty of installation

Pending Publication Date: 2022-04-15
COSCO DALIAN SHIPYARD
View PDF0 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0002] "Maersk Installer" is currently the world's latest ultra-deepwater offshore work vessel. The deck is equipped with two internationally leading new folding-arm offshore cranes with wave compensation function, including the traction winch and rope storage winch of the 400-ton folding-arm crane Arranged inside the cabin, supply and install during the ship construction stage, the main steel wire rope is supplied separately by foreign manufacturers, the delivery time lags behind, and the main steel wire rope is heavy (about 264 tons), and the 200-ton gantry crane on the berth does not meet the lifting requirements. It is impossible to install the main wire rope during the berth construction stage. According to the delivery date of the equipment, after the ship is built and launched, the 400-ton folding arm crane is installed underwater and then the main wire rope is threaded and installed. Because the crane wire rope cannot be directly installed on the rope storage winch Therefore, a deck crane wire rope installation process solution is needed to solve this construction problem

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Ship deck crane steel wire rope installation process method
  • Ship deck crane steel wire rope installation process method
  • Ship deck crane steel wire rope installation process method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0025] like Figure 1 to Figure 6 As shown, the ship deck crane wire rope installation process method includes the following steps: a, install the traction nylon rope 1: manually install the nylon rope 1 according to the trend diagram of the main steel wire rope 4; b, install the first traction wire rope 2 (specification : 18mm in diameter, 300m in length): dock the ship on the edge of the wharf, arrange a 35-ton first rope winding machine 6 at the wharf, install the first traction wire rope 2 with a diameter of ∅18mm, and connect the nylon rope 1 to the first Traction wire rope 2 ends, through the traction winch 8 of the deck crane 7, the nylon rope 1 is received on the reel of the rope storage winch 9, at this time, the first traction wire rope 2 is driven, and it is brought into the winding system, and the wire rope is wound to the coil. When the drum is on, stop winding, take off the nylon rope 1 below the rope storage winch 9 reels; c, install the second traction wire rop...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a ship deck crane steel wire rope installation process method. The method comprises the following steps that a, a traction nylon rope is installed; b, mounting a first traction steel wire rope; c, mounting a second traction steel wire rope; d, hoisting and placing the main steel wire rope transportation winding drum on the second rope winding machine by using a sea crane until a shaft of the second rope winding machine is completely inserted into a central hole of the main steel wire rope transportation winding drum, clamping and locking, switching on a power supply, debugging the second rope winding machine, and checking whether the second rope winding machine is normal or not; e, the PW125 connector is welded to the end of the main steel wire rope, and NDT flaw detection is conducted after welding; f, mounting a main steel wire rope; g, a main steel wire rope entering point is found, the end of the main steel wire rope is placed in a winding drum rope pressing end hole of the rope storage winch, and a bolt is screwed for fixing; h, loosening the main steel wire rope clamp, and continuously winding the main steel wire rope until the main steel wire rope on the main steel wire rope conveying drum is completely separated; i, pouring rope joints; and j, mounting a main hook. The method successfully solves the problem that the crane steel wire rope is difficult to install.

Description

technical field [0001] The invention relates to a process method for installing a steel wire rope of a ship deck crane. Background technique [0002] "Maersk Installer" is currently the world's latest ultra-deep-water offshore work vessel. The deck is equipped with two internationally leading new folding-arm offshore cranes with wave compensation function, including the traction winch and rope storage winch of the 400-ton folding-arm crane Arranged inside the cabin, supply and install during the ship construction stage, the main steel wire rope is supplied separately by foreign manufacturers, the delivery time lags behind, and the main steel wire rope is heavy (about 264 tons), and the 200-ton gantry crane on the berth does not meet the lifting requirements. It is impossible to install the main wire rope during the construction of the berth. According to the delivery date of the equipment, after the ship is built and launched, the 400-ton folding arm crane is installed under...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): B66D1/28B66D1/36B66D1/74
CPCB66D1/28B66D1/36B66D1/741
Inventor 尹龙张平
Owner COSCO DALIAN SHIPYARD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products