[0010] A method for stockpiling red mud, characterized in that the bottom of the red mud dam is composed of a sand filter layer 3, a supporting slab layer 4, a water collecting dark ditch 5 under the supporting layer and a vertical return well 2, and the water collecting dark ditch They are connected by connecting pipe 6 to form a communicating structure.
[0011] When constructing the red mud storage yard, the current anti-seepage standard is adopted to lay the anti-seepage layer, and the sand filter layer is set under the red mud layer, and the water collection dark ditch is set under the sand filter layer. The supporting layer of microporous materials permeable to alkali solution is commercially available porous permeable bricks or porous permeable prefabricated panels, and channels are used to connect ditches and between ditches and backwater wells. When the red mud plant is stockpiling, the red mud 1 attached liquid infiltrates through the red mud layer and passes through...
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More 