Embodiment Construction
[0022] Further illustrate the present invention below in conjunction with accompanying drawing.
[0023] Such as figure 2 Shown, the viaduct bridge large-diameter bored pile construction method within the scope of the tunnel dock type structure of the present invention comprises the following steps:
[0024] (1), determine the construction sequence: first construct the viaduct pile foundation away from the tunnel dock structure 1, and then construct the viaduct pile foundation 2 close to the tunnel dock structure 1;
[0025] (2) Buried casing: In order to overcome the resistance during sinking and reduce the impact on the tunnel structure, the casing is sunk by vibrating excavation method, and the steel casing is submerged in two sections by vibrating hammer to ensure that the tunnel The upper part of the pile body within the scope of the dock structure is surrounded by a steel casing; in order to avoid the deformation of the casing during the burial construction, reinforcin...