Concrete face rockfill dam pre-settling construction method
A technology of concrete slab and construction method, which is applied to dams, barrages, weirs, etc., can solve the problems of casualties of construction equipment, erosion of rockfill dams, limited flood discharge capacity of diversion tunnels, etc., and is conducive to settlement and deformation control. , Accelerate the settlement and deformation, which is beneficial to the safety and stability of the dam body
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment
[0017] a. After the empty steel bar gabion 3 is neatly arranged and welded into one, fill stones in the gabion 3;
[0018] b. Reinforced gabion 3 is stacked along the downstream side slope of the rockfill dam body, and connected with each other by steel bars; after the empty steel gabions are placed neatly and welded into one, the stone cages with a diameter of no more than 70cm are placed with a loader. Blocks are filled in the gabion, and the steel gabion 3 is closed with binding wire;
[0019] c. Use threaded steel bars as the connecting anchor rod 5, and anchor the steel bar gabion 3 with the mountains on both sides. After the water flows through the dam, the water pre-settling is completed.
[0020] The height of the reinforced gabion 3 along the rockfill dam body shall not exceed the filling elevation of the upstream dam surface.
[0021] Reinforced gabion 3 length × width is not less than 300 × 200cm.
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com