A semi-submersible platform and solution technology, applied in ship construction, ship parts, ships, etc., can solve the problems of increasing costs, wasting resources, and low work efficiency, so as to increase the speed of construction, lower construction costs, and improve work efficiency. efficiency effect

Active Publication Date: 2010-08-18
COSCO SHIPPING SHIPYARD (NANGTONG) CO LTD
View PDF5 Cites 15 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

The upper hull part is the main deck, and the lower hull part is composed of two pontoons and four columns, and each pontoon is equipped with two columns. At present, there are two ways to build this type of semi-submersible platform: one is to adopt segmented loading , the construction speed is slow, the integrity of the mechanical completion is poor, and the work efficiency is relatively low; the other is to maximize the use of site resources and speed up the project progress. The lower hull and the upper hull are manufactured separately and at the same time. When they are completed to the maximum, adopt The 20,000-ton gantry crane lifts the upper hull to the lower hull as a whole, which requires a large one-time investment, increases construction costs, and wastes resources

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction program of semi-submersible platform for offshore oil and gas development
  • Construction program of semi-submersible platform for offshore oil and gas development

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0016] In order to deepen the understanding of the present invention, the present invention will be further described in detail below in conjunction with examples. The examples are only used to explain the present invention and do not constitute a limitation on the protection scope of the present invention.

[0017] A specific implementation of the construction scheme of the semi-submersible platform for offshore oil and gas development of the present invention, the semi-submersible drilling platform structure is roughly divided into four areas: 1) the upper deck (mainly including the main deck 1, the residential area and a Helicopter platform): It will carry almost all the equipment required for the work of this drilling platform, and it will also have two cranes arranged on both sides. 2) The second part of the pontoon bridge: it should provide most of the buoyancy required for the platform to float, and its interior is separated by a number of vertical and horizontal bulkheads ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a construction program of a semi-submersible platform for offshore oil and gas development, and comprises the following steps: preparing parts, making an upgrade support, and folding a pontoon and a column into a lower part structure; a plurality of elevating brackets are arranged on the exterior of two sides in the longitudinal direction of a main deck, a plurality of elevating brackets are arranged on the hollow position of two sides in the longitudinal direction of the main deck, a lower elevating lifting point is arranged on a position which corresponds to strong structure of the close lower part of the main deck under the elevating brackets of the interior and the exterior, a elevating beam on the top part of the elevating bracket is provided with pressure synchronous elevating equipment which is connected with lower elevating lifting point on the main deck so as to carry out the overall hydraulic synchronizing elevating and lifting on the main deck, the lower part structure of the main deck is moved under thereof to be in place, and the pressure synchronous lifting equipment slowly lowers to enable the main deck to be located on the lower part structure and to be welded and provided with a tube support structure. The invention has simple operation, time saving and energy saving and improved working efficiency.

Description

Technical field: [0001] The invention relates to a construction scheme of an offshore oil and gas development device, in particular to a construction scheme of a semi-submersible platform for offshore oil and gas development. Background technique: [0002] As the onshore oil reserves are declining, more and more countries have begun to focus on the exploitation of offshore oil, and the market demand for offshore oil rigs will also increase. The upper hull part is the main deck, and the lower hull part is composed of two pontoon bridges and four columns. Each pontoon bridge is equipped with two columns. Currently, there are two methods for constructing this type of semi-submersible platform: one is to use segmented loading In this, the construction speed is slow, the completeness of the mechanical completion is poor, and the work efficiency is relatively low; the other is to make the most of the site resources and speed up the project progress. The lower hull and the upper hull ar...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): B63B9/06
Inventor 倪涛庄建军许智敏屠艳
Owner COSCO SHIPPING SHIPYARD (NANGTONG) CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products