Steel-concrete composite girder construction technology striding current lines and being parallel to existing lines

A steel-concrete combined beam and construction technology technology, applied in bridges, bridge construction, erection/assembly of bridges, etc., can solve the problems of large mutual interference between construction and operation, complex structural design, short construction period, etc., to achieve flexible construction methods, The overall structure of the support is stable and the construction period is short.

Inactive Publication Date: 2011-10-19
THE NO 6 ENG CO LTD OF CHINA RAILWAY 20TH BUREAU GRP
View PDF4 Cites 5 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] Nowadays, there are few steel-concrete composite beam construction projects that cross the existing line and run parallel to the existing line, and the construction process is complicated to varying degrees, requiring a short construction period, high safety risks, and large interference between construction and operation. And other construction characteristics, so the construction is very difficult

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Steel-concrete composite girder construction technology striding current lines and being parallel to existing lines
  • Steel-concrete composite girder construction technology striding current lines and being parallel to existing lines
  • Steel-concrete composite girder construction technology striding current lines and being parallel to existing lines

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0051] Such as figure 1 The construction process of a steel-concrete composite beam that crosses the existing line and runs parallel to the existing line includes the following steps:

[0052] Step 1. Erection of the supporting frame: the supporting frame includes a plurality of temporary buttresses arranged between the two piers from left to right.

[0053] combine figure 2 , image 3 with Figure 4 , the constructed steel-concrete composite beam 1 is erected between two left and right bridge piers, the newly-built line where the steel-concrete composite beam 1 is located is parallel to the existing operating line and it crosses the existing operating line 3, and the two bridge piers They are respectively a left pier 6-1 and a right pier 6-2 arranged one left and one right, and the left pier 6-1 and the right pier 6-2 are both equipped with mounting supports. The steel-concrete composite beam 1 includes a steel beam body composed of a plurality of steel beam segments 1-1...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a steel-concrete composite girder construction technology striding over current line and being parallel to existing lines, which comprises the flowing steps: firstly, erecting a supporting falsework, wherein the supporting falsework comprises a plurality of temporary buttresses which are distributed between two buttresses from left to right, and the distribution positions of the plurality of temporary buttresses respectively correspond to the connection position of two adjacent steel grinder sections of a steel grinder body in a construction steel-concrete composite girder; secondly, hoisting the steel grinder sections, wherein a plurality of steel grinder sections constituting the steel grinder body are hoisted in place one by one; thirdly, splicing the steel grinder body, wherein splicing is conducted on the steel grinder body after linetype adjustment and camber adjustment; fourthly, converting the system; fifthly, conducting concrete pouring construction on a ballast channel plate; and sixthly, detaching the supporting falsework. The steel-concrete composite girder construction technology has reasonable design, convenience in the construction, low investment cost, good using effect, high construction efficiency, short construction period and low safety risk, and the adopted supporting falsework has a simple structure and high satiability and is economical and practical.

Description

technical field [0001] The invention belongs to the technical field of steel-concrete combined beam construction, and in particular relates to a construction technique for steel-concrete combined beams spanning existing lines and running parallel to existing lines. Background technique [0002] Such as figure 2 As shown, the reconstruction of the second line project of the Xiangyu Line of the railway (that is, the new line under construction) from Ankang to Liangjiaba section, YD1K463+927.56 Houhe No. 10 Right Line Bridge has a total of 16 spans and a total length of 507 meters. Proximity to the exit end of Wanyuan Railway Station. The new line runs parallel to the existing Houhe No. 10 Bridge (the existing railway operation line 2, referred to as the existing line), and the distance between the two lines is 5.50m-5.52m. During the actual construction, the 1st to 10th spans of the new line pass through the main urban area of ​​Wanyuan City, Sichuan Province. Among them, th...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E01D21/00
Inventor 王剑武群虎颜立宏冯晓强王柳新汪东瑞何涛赵国庆程刚
Owner THE NO 6 ENG CO LTD OF CHINA RAILWAY 20TH BUREAU GRP
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products