A drilling and cementing, low-pressure oil technology, applied in drilling equipment, wellbore/well components, earth-moving drilling, etc., can solve problems affecting oil reservoir development and production, lost circulation, poor cementing quality, etc. The effect of cementing quality, loss reduction and additional reduction
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0014] Such as figure 1 , figure 2 As shown, a low-pressure oil reservoir sidetracking well cementing and completion process includes the following steps:
[0015] A. Reaming the original wellbore 1 after the sidetracking well in the low-pressure oil reservoir is completed;
[0016] B. After the reaming is completed, run a completion casing into the reamed wellbore 2;
[0017] C. Run into the U-shaped tube low-pressure cementing device 3;
[0018] D. Running into the well completion casing with cement umbrella 4 installed;
[0019] E. Use low-density cement slurry to cement the well.
[0020] It can be understood that the above specific descriptions of the present invention are only used to illustrate the present invention and are not limited to the technical solutions described in the embodiments of the present invention. Those of ordinary skill in the art should understand that the present invention can still be modified or Equivalent replacements to achieve the same t...