Control system for integrated synchronous jacking of cut pier and control method

A technology of overall jacking and synchronous jacking, applied in bridges, bridge maintenance, bridge reinforcement, etc., can solve the problems of slow jacking speed, great subjectivity, and low control accuracy.

Active Publication Date: 2013-11-13
CHINA RAILWAY FIRST GRP CO LTD
View PDF5 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0004] Nowadays, in the overall jacking construction process of cutting piers, the above-mentioned unbalanced height difference limit control method is widely used, but due to the cross operation of geometric measurement and jacking work, the overall jacking work of cutting piers is discontinuous
At the same time, since it is difficult to continuously monitor the unbalanced height difference on both sides of the cover beam during the jacking process, the unbalanced height difference will exceed the limit; and because the geometric measurement generally needs to stop the jacking operation, Therefore, the jacking speed is slow, which has a great impact on the construction efficiency; in addition, the oil pump operation control adopts manual control methods, and the entire operation process is subject to greater subjectivity, so the process control accuracy is low

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Control system for integrated synchronous jacking of cut pier and control method
  • Control system for integrated synchronous jacking of cut pier and control method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0052] Such as figure 1 , figure 2 As shown, the overall synchronous jacking control system for cutting piers according to the present invention includes two hydraulic jacking devices for providing jacking power and lifting the bridge structure that needs to be integrally jacked up horizontally. The two hydraulic circuits connected by the hydraulic jacking device, the two oil inlet adjustment devices respectively installed on the two hydraulic circuits, and the real-time monitoring of the balance state of the bridge structure that needs to be lifted as a whole during the jacking process A jacking balance state monitoring device that monitors and controls the two oil inlet adjustment devices accordingly according to the monitoring results.

[0053] The two hydraulic jacking devices are respectively a hydraulic jacking device 1 and a hydraulic jacking device 2 under the left and right sides of the bridge structure that needs to be integrally jacked up, and the two hydraulic ci...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a control system for integrated synchronous jacking of a cut pier and a control method. The control system comprises two hydraulic jacking devices for providing jacking power, two hydraulic circuits connected with the two hydraulic jacking devices respectively, two oil feeding amount adjusting devices and a jacking balancing state monitoring device, wherein the two oil feeding amount adjusting devices are installed on the two hydraulic circuits respectively, and the jacking balancing state monitoring device performs real-time monitoring to a balancing state of a structure needing to be jacked in the jacking process and controls the two oil feeding amount adjusting devices according to monitoring results. The control method comprises the steps of jacking preparation and jacking, upward jacking is performed to the structure through the two hydraulic jacking devices in actual jacking until the structure is jacked to a preset height, and timely dynamic deviation rectification is carried out to the structure. The control system for integrated synchronous jacking of the cut pier and the control method are reasonable in design, high in automation, good in coordinating performance and safety performance and simple and convenient to control, enables the jacking process to be smooth and efficient, and can effectively solve the construction problem that unbalanced elevation discrepancy limitation in the pier cutting integration jacking process cannot be automatically controlled.

Description

technical field [0001] The invention belongs to the technical field of bridge structure jacking construction, and in particular relates to a control system and a control method for synchronous jacking up of a cut bridge pier as a whole. Background technique [0002] The use of multiple jacks to realize synchronous lifting of the structure is a commonly used construction method with relatively high technical difficulty in bridge construction. In actual construction, the key to construction control is to realize the simultaneous operation of multiple jacks and the stable lifting of the jacked structure. At present, the synchronous jacking construction control mainly controls the jacking speed of each jack through the method of on-site geometric measurement combined with manual switching of the oil pump. This traditional control method has high requirements for structural geometric measurement, and the measurement operation and switching oil pump need to be jacked up and constr...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Patents(China)
IPC IPC(8): E01D22/00
Inventor 徐宏范恒秀许铁力唐明孙兆兴
Owner CHINA RAILWAY FIRST GRP CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products