Industrial manipulator applicable to automatic arrangement and welding of solar photovoltaic cell
An industrial manipulator, photovoltaic cell technology, applied in manipulators, program-controlled manipulators, welding equipment, etc., can solve the problems of lack of handling auxiliary tools, low position accuracy, poor welding quality, etc., to achieve simple structure, reduce costs, and reduce accidents. The effect of incidence
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Publication Date
- 2012-07-04
Smart Images
Figure 1 Figure 2 Figure 3
Abstract
Description
technical field
[0001] The invention relates to an industrial manipulator, in particular to an industrial manipulator suitable for automatic arrangement and welding of solar photovoltaic cells. Background technique
[0002] At present, the domestic solar photovoltaic cell industry is booming, and its output ranks first in the world. Among them, the first-generation crystalline silicon solar cells account for 80% of the market share, but there are many problems in the production process when individual crystalline silicon bodies are welded together to form panels. question. At present, most of the welding work for solar photovoltaic cells is done manually to complete the clamping, handling and welding of workpieces between various processes, which cannot be precisely positioned and controlled, and the production efficiency is not high. When welding solar photovoltaic cells currently used, multiple people are required to complete the entire welding process, which has low effi...
Examples
Embodiment Construction
[0018] The present invention will be further described below in conjunction with the accompanying drawings and embodiments.
[0019] Such as figure 1 , figure 2 As shown, the present invention includes a base 1, a slide rail 2, a timing belt 3, a timing belt adjusting device 4, a timing belt fixing device 5, a welding bench 6, a first manipulator 8, a second manipulator 9, a third manipulator 10, a control Cabinet 7, jig one 19 and jig two 22. The base 1 is a Π-shaped structure, two slide rails 2 are installed in parallel on the top of the base 1, and the first manipulator 8, the second manipulator 9 and the third manipulator 10 are respectively installed on the slide rails 2 from left to right. The welding bench 6 is arranged directly behind the base 1 . One end of the synchronous belt 3 is fixed on the synchronous belt adjusting device 4 , and the other end is fixed on the synchronous belt fixing device 5 . The synchronous belt adjusting device 4 is fixed on the left en...