Construction method for CRD (center cross diaphragm) inverted arch
A construction method, I-beam technology, applied in earthwork drilling, shaft lining, tunnel lining, etc., to achieve the effects of reducing construction costs, avoiding frequent conversions, and high safety
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment Construction
[0015] A kind of CRD inverted arch construction method described in the embodiment of the present invention, comprises the following steps:
[0016] 1) Set temporary steel support: the temporary steel support is replaced by I-beam 22a in the middle partition, and the distance between the temporary steel support is 2.0m;
[0017] 2) Remove the middle partition near the temporary steel support: remove the middle partition near the temporary steel support with a width of 1.0m and below the outline of the inverted arch, and cut off the steel body within the range of 80-100mm at the bottom of the I-beam;
[0018] 3) Apply leveling layer, waterproof layer and protective layer on the bottom surface of the temporary steel support: apply a leveling layer, waterproof layer and 60mm thick fine stone concrete protective layer in the scope of the temporary steel support 80cm×80cm;
[0019] 4) Applying prestress: place a steel plate with a size of 300mm×300mm×10mm on the bottom surface of t...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com