Operation workshop scheduling key outside cooperation process identification method based on relation chains

A job shop and relationship chain technology, applied in the field of job shop scheduling key outsourcing process identification based on relationship chain, can solve the problems of complex optimization algorithm solution process, inability to give alternative solutions, poor pertinence, etc.

Active Publication Date: 2013-04-03
NORTHWESTERN POLYTECHNICAL UNIV
View PDF2 Cites 13 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

In general, the optimization algorithm has a complicated solution process, and the calculation time of the algorithm is relatively long. It stays at the level of academic research and is difficult to be understood by production managers, which limits the popularization and application of related model algorithms.
In addition, on the

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Operation workshop scheduling key outside cooperation process identification method based on relation chains
  • Operation workshop scheduling key outside cooperation process identification method based on relation chains
  • Operation workshop scheduling key outside cooperation process identification method based on relation chains

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0047] Describe the present invention below in conjunction with specific embodiment:

[0048] In this embodiment, the standard calculation example FT06 in the job shop (Job Shop) scheduling problem is taken as an example.

[0049] In this embodiment, the flow chart of the key outsourcing procedure identification method for job shop scheduling based on the relationship chain is shown in figure 1 .

[0050] Specific steps are as follows:

[0051] Step 1: Solve the job shop scheduling problem to be identified, and obtain the initial scheduling plan C of the job shop: the initial scheduling plan C includes the total number of machines m, the total number of workpieces n, and the processes processed on the sth order of the kth machine Information: process number, workpiece number, process start time, process end time; the processing of each workpiece consists of m processes.

[0052] The optimal solution of the FT06 standard calculation example was obtained by M.Florian in "AN I...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention provides an operation workshop scheduling key outside cooperation process identification method based on relation chains. The method comprises the steps of first obtaining initial scheduling according to the scheduling problem; then identifying candidate key outside cooperation processes according to processing rules of the relation chains; then re-scheduling the processes influenced after outside cooperation; and finally performing multi-attribute decision making according to the conditions of the production site, and outputting an optimal key outside cooperation process and a corresponding production scheduling scheme. By applying the method, a process set restraining effective throughput of the whole scheduling scheme can be found out rapidly in a targeted mode, and blind and passive searching for the outside cooperation processes is avoided. To solve the scheduling problem for an operation workshop with m machines and n workpieces, tests need doing for m*n times in an exhaustive method. According to the operation workshop scheduling key outside cooperation process identification method, the minimum transfer times is m, the maximum transfer times is m*n-1. Through the tests done for 100 times, the obtained average transfer times is about (m*n-1)/3.

Description

technical field [0001] The invention relates to the technical field of job shop procedure identification, in particular to a method for identifying key outsourcing procedures for job shop scheduling based on relationship chains. Background technique [0002] There are often limited equipment resources and unbalanced equipment utilization in the workshop. On the one hand, production management personnel make full use of the company's own resources through "internal potential tapping", and on the other hand, through product outsourcing or process outsourcing, use external resources and rationally allocate internal and external resources to make the overall production system optimal. Considering the limited room for improvement of "internal potential tapping" of enterprises, product outsourcing or process outsourcing has gradually become the focus of enterprise practice. Product outsourcing refers to subcontracting the entire product in multiples, and process outsourcing refer...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
IPC IPC(8): G06Q10/06
Inventor 王军强王烁郭银洲崔福东张承武杨宏安张映锋孙树栋
Owner NORTHWESTERN POLYTECHNICAL UNIV
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products