Diaphragm wall construction method across deep buried large municipal pipelines
A construction method and municipal technology, applied in the direction of sheet pile wall, foundation structure engineering, construction, etc., can solve the problems of conflict between the enclosure structure and the existing pipeline, failure to complete the groove, mud loss, etc., and achieve strong construction operability, The effect of time saving, cost and construction period reduction
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0020] This embodiment is a method for constructing a diaphragm wall across a large deep-buried municipal pipeline, so as to avoid the problem that a large amount of mud used for the retaining wall of the diaphragm wall will be lost from the pipeline during the construction of the diaphragm wall, and the construction is convenient and the cost is low. The concrete construction method of this embodiment is as follows:
[0021] a. Find and close the front and rear gates of municipal pipeline 1 passing through section 2 of the diaphragm wall to be constructed before construction, and pump out the water in this section of municipal pipeline or keep the water in the pipeline in a non-flowing state;
[0022] b. Such as image 3 As shown, on both sides of the diaphragm wall 2 and directly above the municipal pipeline 1, a steel casing 3 is used to protect the wall, and the hole is drilled to the top of the municipal pipeline 1, and the steel casing 3 is overlapped with the municipa...