A construction method and carrier pile technology, applied in sheet pile wall, foundation structure engineering, foundation structure test and other directions, can solve the problems of difficulty in completing larger and longer diameter piles, difficult application, etc., to expand application types and Scope of application, low equipment cost and construction cost, and the effect of improving hole forming speed

Active Publication Date: 2015-10-21
王继忠 +1
View PDF6 Cites 6 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

However, due to the limitation of construction equipment and construction methods, it is difficult to complete piles with larger diameter and longer piles, so it is difficult to apply in projects with high bearing capacity requirements.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method for carrier pile of major diameter long pile
  • Construction method for carrier pile of major diameter long pile

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0034] The present invention will be further described below in conjunction with the accompanying drawings.

[0035] figure 1 It is the process drawing of an embodiment of the construction method of the concrete pile of the large-diameter long pile of the present invention, and the hole forming of the pile body of this embodiment adopts the method of squeezing the soil to form the hole. At first, as figure 1 As shown in a, at the pile position in the foundation, by applying vibration force to the A casing 1, the A casing 1 with the prefabricated pile tip 2 is sunk to the set depth; then, as figure 1 As shown in middle b, in the inner cavity of A casing 1, the B casing 3 whose length is greater than A casing 1 is sunk; then, as figure 1 As shown in c, the vibration force is applied to the B casing 3, and the B casing 3 drives the prefabricated pile tip 2 to sink down to the set depth; then, as figure 1 As shown in middle d, a certain amount of filling material 4 is filled in ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

An objective of the invention is to provide a construction method for a carrier pile of a major diameter long pile. A method of alternate double casing is used, and aimed at different soil layers, a plurality of means are selected, so as to complete large diameter and large depth pile body pore forming. Then carrier construction is performed on a pile tip, obviously improving carrying capacity of a pile and improving work efficiency and saving cost. The method comprises steps: 1) using a double casing pipe method to perform pore forming construction, soil-squeezing pore forming steps: making an A pile casing with a pile tip sink, making a B pile casing sink in the A pile casing and making the B pile casing sink to a set depth, soil-taking pore forming steps: making the open A pile casing sink and then taking soil mass in the A pile casing out, making the B pile casing sink in the A pile casing, and making the B pile casing sink to the set depth again, and taking soil mass in the B pile casing out; 2) according to soil layer property and upper load requirement, performing reinforcement treatment of the pile end through one of a plurality of methods, so that soil mass at a certain depth under the pile end and in a certain range are reinforced and compacted to form a pile end carrier, to realize equivalent calculation area Ae of the carrier pile; 3) and performing cast-in-place or precast concrete pile body construction through one of a plurality of methods.

Description

technical field [0001] The invention relates to the field of civil engineering, in particular to the construction of piles. Background technique [0002] With the development of my country's economic construction, there are more and more construction projects such as bridges, elevated railways, high-rise buildings, etc., and the requirements for the bearing capacity of foundation piles are also getting higher and higher. At present, piles with a bearing capacity of more than 2000kN are generally used. The method of increasing the pile diameter and increasing the pile length is to increase the friction force and end resistance of the pile to achieve the purpose of improving the bearing capacity of the pile. However, the project cost of such large pile diameter and long pile is very high. The reason is that the consumption of building materials is very large, and the second is that the requirements for construction equipment are high. It is difficult to form holes, especially ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E02D5/62E02D5/38E02D5/50E02D33/00
Inventor 王继忠
Owner 王继忠
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products