Tool changing construction method for in-chamber grouting of earth pressure balance shield machine in sand bed
A technology of earth pressure balance and construction method, which is applied in earth-moving drilling, wellbore lining, tunnel lining and other directions, can solve the problems of unclear grouting construction operation method, poor air-holding ability of sand layer, and easy blockage of grouting port, etc. Achieve the effect of avoiding advanced grouting construction operations, shortening construction time and reducing construction workload
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0041] The present invention will be described in detail below in conjunction with specific embodiments. The following examples will help those skilled in the art to further understand the present invention, but do not limit the present invention in any form. It should be noted that those skilled in the art can make several modifications and improvements without departing from the concept of the present invention. These all belong to the protection scope of the present invention.
[0042] Such as Figure 1-3 As shown, this embodiment provides a construction method for grouting and tool change in the earth pressure balance shield machine chamber in the sand layer, which is used in a tunnel in Guangzhou; the depth of the bottom of the shield machine cutter head is 14m underground, and the ground above the stop position is At intersections, in order to prevent damage to the structure of the cutter head due to excessive wear, bursting and jamming of the cutter, which will affect...
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More 