Cold seam treatment method of canal-type cement-soil continuous wall
A treatment method and soil-cement technology, applied in sheet pile walls, water conservancy projects, underwater structures, etc., can solve problems such as pipeline damage, damage to underground pipelines, complicated and inconvenient operations, and achieve the effect of ensuring impermeability.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0028] Example 1: as figure 1 As shown in the figure, a cold joint treatment method for a canal-type cement-soil continuous wall includes the following steps in sequence:
[0029] A: Construct the front channel-type cement-soil diaphragm wall 1 along the wall-building direction in the foundation soil layer, and the horizontal distance between the front-section channel-type soil-cement diaphragm wall and the pipeline 3 in the foundation soil layer is L1 meter. The value of L1 in this embodiment is 0.4 or 0.6 or 0.8 or 1 or 1.2 meters.
[0030] B: Construct the rear canal-type cement-soil continuous wall 5 along the wall-building direction in the foundation soil layer. The horizontal distance between the back channel-type cement-soil diaphragm wall and the pipeline in the foundation soil layer is L2 meters. The value of L2 in this embodiment is 0.4 or 0.6 or 0.8 or 1 or 1.2 meters. The height of the front channel-type cement-soil diaphragm wall is the same as that of the rear...
Embodiment 2
[0034] Embodiment 2: a cold seam treatment method for a channel-type cement-soil diaphragm wall, comprising the following steps in turn:
[0035] A: The front channel-type cement-soil diaphragm wall is constructed along the wall-building direction in the foundation soil layer, and the horizontal distance between the front-end channel-type cement-soil diaphragm wall and the pipeline in the foundation soil layer is L1 meters. The value of L1 in this embodiment is 0.4 or 0.6 or 0.8 or 1 or 1.2 meters.
[0036] B: Construct the rear canal-type cement-soil diaphragm wall along the wall-building direction in the foundation soil layer. The horizontal distance between the back channel-type cement-soil diaphragm wall and the pipeline in the foundation soil layer is L2 meters. The value of L2 in this embodiment is 0.4 or 0.6 or 0.8 or 1 or 1.2 meters. The height of the front channel-type cement-soil diaphragm wall is the same as that of the rear channel-type cement-soil diaphragm wall...