Power transmission and transformation system risk early warning method

A risk early warning, power transmission and transformation technology, applied in the field of risk early warning of power transmission and transformation systems, can solve the problems of difficult data acquisition, time-consuming, fixed parameters, etc., to achieve the effect of shortening the fault inspection time, reducing the inspection scope, and improving efficiency

Inactive Publication Date: 2017-05-10
STATE GRID CORP OF CHINA +1
View PDF3 Cites 7 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

Risk assessment is a complex and time-consuming task in all industries. Since the assessment results are mixed with a large number of subjective factors, the accuracy of the mathematical model for assessment is low and the compatibility is poor.
In the electric power industry, the main problems in the current risk assessment of transmission lines are: 1. The evaluation method is simple, the parameters are fixed, and the convincing results are limited
2. It is difficult to obtain data, the information is incomplete, the assessment is not comprehensive enough, and the assessment results cannot truly reflect the risk situation of the equipment
3. Status assessment and risk assessment are out of touch. Most power grid companies only conduct status assessment, and follow-up maintenance and risk assessment work no longer pay attention
4. Low-accuracy and incomplete risk assessment reports cannot reflect the real risks of equipment, and the assessment results often have limited impact on maintenance decisions, so they cannot strongly support the maintenance decision-making

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0011] The technical solutions in the embodiments of the present invention are clearly and completely described below.

[0012] In an embodiment of the present invention, a risk early warning method for a power transmission and transformation system includes the following steps: step S1, establishing an overall framework for risk assessment of a transmission line, establishing a risk assessment model for each component of a transmission line, and establishing the quantification and Obtain the degree of membership; step S2, establish the calculation method and evaluation standard for the correction of the risk value of the transmission line by the equipment operation period, the operation environment and the operation state of the power grid, and define the aging coefficient of the components, the operation environment time coefficient and the geographical location coefficient of the transmission line; In step S3, the overall risk value of the transmission line is obtained from ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a power transmission and transformation system risk early warning method. The method includes the following steps that: S1, a power transmission line risk assessment establishing overall framework is established, a risk assessment model is established according to each component of a power transmission line, the quantization of state quantities is established, and the degrees of membership of the state quantities are solved; and S2, a calculation method and an evaluation standard for the correction of the risk value of the power transmission line by the operating years and operating environment of equipment and the operation status of a power grid are determined, and the aging coefficients of the components, the operating environment time coefficient and geographical position coefficient of the power transmission line are defined. With the power transmission and transformation system risk early warning method of the invention adopted, an interval of the power transmission line, where a fault occurs, can be determined more accurately, fault inspection can be performed in a targeted manner, the inspection range of line fault inspectors can be decreased, line fault inspection time can be decreased, the cause of the fault of the power transmission line can be determined more accurately, and the efficiency of fault analysis can be improved.

Description

technical field [0001] The invention relates to an early warning method, in particular to a risk early warning method for a power transmission and transformation system. Background technique [0002] The continuous expansion of the scale and increasing importance of the power system has made the society have higher requirements for the reliable operation of the power system. Electric workers not only need to solve the existing problems, but also need to understand the possibility of equipment problems and the severity of the problems through risk assessment. Not only that, the data of risk assessment are often used in the operation and maintenance scheduling of the power grid, and can play a guiding role in the operation monitoring, maintenance management, fault handling, and on-site inspection of power companies. At the same time, the environment of overhead transmission lines is complex and changeable, and the operation status is seriously affected by rain, snow, lightnin...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): G06Q10/06G06Q50/06
CPCG06Q10/0635G06Q50/06
Inventor 刘彦文张丙涛李晓旭崔勇王子刚张玉超王娟
Owner STATE GRID CORP OF CHINA
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products