A vertical adjustment method for integrated construction of steel pipe columns
A technology of steel pipe columns and steel pipes, which is applied in the vertical adjustment field of integrated construction of steel pipe columns, can solve problems such as low construction efficiency, huge equipment, and unusability, and achieve the effects of improving construction safety, saving installation time, and reducing construction costs
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
specific Embodiment approach
[0013] The preferred embodiment of the vertical adjustment method for steel pipe column integrated construction of the present invention is:
[0014] Use a total station to place the center point of the steel pipe column on the vault of the small pilot tunnel, and place the longitudinal axis of the pile on both sides of the pilot tunnel. The PE line is tied to the center point. After the installation of the steel pipe column is completed, lead this line from the inside of the steel pipe column to the center point of the vault pile, and straighten the line to ensure that the two points are on a straight line. Install the positioning cross line at the upper flange of the steel pipe column, then pull the longitudinal axis where the pile is located, and use a total station to locate the center point of the pile on the longitudinal axis, and finally use the chuck to adjust the position of the steel pipe column so that the center of the column bottom and the column top The four poin...
specific Embodiment
[0058] like Figure 1-Figure 3 As shown, the present invention provides a construction method for integrated vertical adjustment of piles. The construction method uses mechanical rapid integrated construction of piles in a narrow space, thereby improving construction safety.
[0059] The specific technical scheme is as follows:
[0060] 1. Integrated construction and setting out of piles
[0061] Before the construction, use the wire control points in the leading hole, and use the Leica total station TS06 to place points on the center of the construction pile. The laser function of the instrument can be directly placed on the vault, and the cement nails are manually fixed on the vault and made. Good mark.
[0062] There are two longitudinal axes of the columns on both sides of the guide tunnel wall. The vertical distance between the two longitudinal axes should be 1m, and the center point of the columns should be placed on the longitudinal axis and marked.
[0063] Second, ...