Advanced construction method for masonry wall anchoring reinforcement
A construction method and technology of pulling wall reinforcement, which is applied in the direction of construction and building construction, can solve the problems of poor welding of reinforcement, drilling of formwork, affecting structural safety and applicability, etc., to save costs and reduce drilling noise , The effect of saving the cost of planting glue materials
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0031] The present invention will be further described below in conjunction with the examples, the purpose is only to better understand the contents of the present invention, therefore, the examples given do not limit the protection scope of the present invention.
[0032] see figure 1 , figure 2 , a method for constructing masonry tensioned wall reinforcement in advance, comprising the steps of:
[0033] The first step, structural column or wall reinforcement binding:
[0034] Carry out the binding and lapping or mechanical connection construction of the structural main reinforcement 4 according to the steel bar diagram in the drawing, and then carry out the construction of the structural stirrup 3.
[0035] The second step is to pull the wall reinforcement 5 to measure and position the wires:
[0036] After the structural column or the wall reinforcement is installed, measure and locate the height position of the tension wall reinforcement 5 on its structure according to...