Bridge precast pier body installation positioning guide device and construction method thereof
A technology for installing positioning and guiding devices, which is used in bridges, bridge construction, erection/assembly of bridges, etc., and can solve problems such as difficult control of position accuracy and damage to surrounding components.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0054] Such as Figure 1~4As shown, a bridge prefabricated pier body 11 is installed with a positioning guide device, including:
[0055] Bottom plate 1, which is a rectangular parallelepiped plate structure, is provided with a reserved hole 6 for installation on the bottom plate 1, on which is provided with an implanted anchor screw 8 and a nut 9, and the bottom plate 1 is connected with the implanted anchor screw 8 and nut 9. Bearing platform 12 is fixed.
[0056] The guide side wing plate 2 is composed of a lower vertical plate and an upper curved panel. The vertical plate of the guide side wing plate 2 is vertically arranged on one side of the bottom plate 1, and the bottom plate 1 is installed on one side of its long side The vertical guide flank plate 2 is formed by welding steel plates with a certain thickness. The upper curved panel of the guide side wing plate 2 is convenient for the prefabricated pier body 11 to slide down to the bearing platform 12 along the curve...
Embodiment 2
[0067] Such as Figure 5 , Figure 7-9 As shown, a bridge prefabricated pier guide installation positioning construction method, including the following steps:
[0068] Step 1. Set up 8 sets of positioning and guiding devices on the cap, and set them in groups of two on the four sides corresponding to the inner side of the prefabricated pier body, and the guiding side panels are set towards the inner side of the prefabricated pier body. The positioning and guiding devices and The distance between the prefabricated pier body setting positions is 5-10mm, which is used as the lowering operation space for the prefabricated pier body (11) of the bridge.
[0069] Step 2. Each positioning guide device is fixed to the platform through the installation reserved hole, implanted anchor screw and nut, and the pre-embedded steel bar 10 on the platform passes through the first steel bar reserved hole and the second steel bar reserved hole ;
[0070] Step 3. Prefabricated pier body is hoi...
Embodiment 3
[0082] Such as Figure 6 As shown, a bridge prefabricated pier external guide installation and positioning construction method is characterized in that it includes the following steps:
[0083] Step 1. Install 8 sets of positioning and guiding devices on the platform cap, and set them in pairs on four sides corresponding to the outer sides of the prefabricated pier body. The distance between the set positions of the pier body is 5-10 mm, which is used as the lowering operation space for the prefabricated pier body (11) of the bridge;
[0084] Step 2. Each positioning guide device is fixed to the bearing platform through the installation reserved hole, implanted anchor screw and nut, and the pre-embedded steel bars on the bearing platform pass through the first steel bar reserved hole and the second steel bar reserved hole;
[0085] Step 3. Prefabricated pier body is hoisted and lowered, and the prefabricated pier body is preliminarily guided by the upper curved panel of the g...