The construction method of synchronous transfer of the starting pipeline of shield tunneling
A technology of separate origination and construction method, which is applied in the direction of earthwork drilling, mining equipment, tunnels, etc., can solve the problems of pipeline damage, prolong the construction period of tunnels, etc., and achieve the effect of saving construction period and simple processing
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0046] The mileage from 1# Fengjing to 2# Fengjing section of a certain line of Chengdu Metro is ZDK66+876.111~ZDK68+772.569, the total length of the section is 1896.458m; the mileage from the right line is YDK66+876.111~YDK68+790.601, the total length of the section 1914.49m; the line spacing is 7.9-19 meters, the buried depth of the tunnel is 6-13 meters, the minimum curve radius is 600m, and the maximum longitudinal slope is 11‰. The interval tunnel is excavated by two CCTC and Φ8580 earth pressure balance shield machines, both of which originate from the large mileage end of the 1# wind shaft and receive at the short mileage end of the 2# wind shaft.
[0047] Since the length of the originating shaft of No. 1 wind shaft in the Ming-Jiu interval is only 66.6m, while the length of the shield machine is 105.5m, the originating shaft cannot satisfy the overall origination of the shield machine. To synchronize the amount of grouting, 6 soil buckets and 2 mortar trucks are requi...