Temporary prestressing structure for prefabricating segment splice-installing type bridge
A technology of prestressed structures and segmental beams, which is applied in erection/assembly of bridges, bridges, bridge construction, etc., can solve problems affecting the local strength of bridges, hidden dangers of bridge durability, etc., and achieve the effect of ensuring integrity and saving construction time
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0030] A U-shaped segmental beam with two webs is selected, and its segment is integrally cast with concrete. The prefabricated segment of the concrete beam is divided into two parts: the bottom plate and the flange plate (web). The beam is 29.4m long and 2.2m high. The top width is 9.928m, and the bottom width is 7.706m; there are two flange plates, which are respectively arranged at both ends of the bottom plate, and the support adopts double-point support of the beam. Each span beam is composed of 10 segment beams, each about 40t.
[0031] The upper surface plane of the bottom plate and the plane at the top of the web are used as the outer surface 1, and grooves are made at the intersecting position of the section 2 to form a cubic groove 3 that runs through the outer surface 1 and the section 2; the groove 3 is a cuboid (without the top surface) and front face).
[0032] In the groove 3, only one elevation (i.e., the rear end face of the cuboid) is parallel to the section...
Embodiment 2
[0047] Box-shaped segmental beams are selected, which are cast in one piece. Each span beam is composed of 10 segmental beams, each about 40t.
[0048] Make grooves at the intersection position of the upper outer surface 1 of the bottom plate and the cross section 2, and make grooves at the intersection position of the upper outer surface 1 of the top plate and the cross section 2 to form a cubic groove 3 passing through the outer surface 1 and the cross section 2; the rest of the structure and construction methods are implemented in the same way example 1.
[0049] After the splicing and other constructions of the various segments of the overall bridge are completed at last, after the permanent prestressed fastening is carried out, the length of the beam group of the bridge segment is longer, and the screw connector 9 can be removed in sections from the groove 3 in the middle, and then the long screw can be used to Deformable feature, directly extract the respective stretchin...