A construction method and hydraulic tank technology, applied in bridges, bridge construction, erection/assembly of bridges, etc., can solve problems such as non-reuse, high cost of curved box girders, difficulty in construction, etc., to prevent water evaporation and save energy Water resources and labor costs, and the effect of reducing construction costs
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0027] The present invention will be further described in detail below in conjunction with the accompanying drawings, so that those skilled in the art can implement it with reference to the description.
[0028] It should be understood that terms such as "having", "comprising" and "including" as used herein do not entail the presence or addition of one or more other elements or combinations thereof.
[0029] Such as Figure 1-4 As shown, the present invention provides a kind of integral hydraulic box girder formwork construction method, and concrete steps comprise:
[0030] Step 1. According to the drawings of the bridge to be constructed, divide the bridge into multiple curved sections and multiple straight sections, and obtain the space alignment of the box girders of the multiple curved sections. The pouring method of the straight section of the box girder is carried out;
[0031] Step 2, erection of the construction platform 4: determine the orientation of the constructi...