Construction method of flexible connecting structure between prefabricated components and building bodies
A technology of prefabricated components and building main body, applied in the direction of building structure, building, building components, etc., can solve the problems of high overall rigidity, inconvenient construction, increase design rigidity, etc., and achieve broad application prospects, simple structure, and convenient construction Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0035] Such as figure 1 As shown, the construction method of the flexible connection structure between the prefabricated component and the main body of the building in this embodiment, wherein the flexible connection structure between the prefabricated component and the main body of the building includes a multi-layer cast-in-place building main body 2 arranged at intervals from top to bottom, two adjacent existing Prefabricated components 1 are connected between poured building main bodies 2 . In this embodiment, the main body 2 of the cast-in-place building is a floor slab, and the prefabricated component 1 is a prefabricated toilet. The lower parts of the four side walls of the prefabricated component 1 shrink inward to form a tenon 11 , and the upper part of the prefabricated component 1 forms the main body of the prefabricated component. A suspension hook 4 is pre-embedded in the upper part of the prefabricated component body.
[0036] The flexible connection method com...
Embodiment 2
[0045] Such as figure 2As shown, the construction method of the flexible connection structure between the prefabricated component and the main body of the building in this embodiment, wherein the flexible connection structure between the prefabricated component and the main body of the building includes a multi-layer cast-in-place building main body 2 arranged at intervals from top to bottom, two adjacent existing Prefabricated components 1 are connected between poured building main bodies 2 . In this embodiment, the main body 2 of the cast-in-place building is a floor slab, and the prefabricated component 1 is a prefabricated toilet. The lower parts of the three side walls of the prefabricated component 1 shrink inward to form a tenon 11 , and the upper part of the prefabricated component 1 forms the main body of the prefabricated component. The upper part of the main body of the prefabricated component is pre-embedded with a hook 4 . The outer wall of the unshrunk side wa...
PUM
Property | Measurement | Unit |
---|---|---|
Thickness | aaaaa | aaaaa |
Thickness | aaaaa | aaaaa |
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com