Method for jacking construction of bridge
A construction method and jacking technology, which is applied to bridges, bridge construction, erection/assembly of bridges, etc., can solve the problems of low jacking construction efficiency and inconvenience, and achieve the goals of accelerating jacking construction efficiency, avoiding subsidence, and reducing pressure Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0058] Embodiment one: if figure 1As shown, it is a bridge jacking construction jacking mechanism disclosed in the present invention, which includes a distribution beam 2 fixed on the lower end surface of the box girder 1 and a jacking mechanism arranged between the distribution beam 2 and the ground.
[0059] Such as figure 1 , 2 As shown, a distribution beam 2 is arranged on both sides of the bridge pier 24 , and the length direction of the distribution beam 2 corresponds to the width direction of the box girder 1 . The jacking mechanism includes a jacking cylinder 3 arranged on the lower end surface of the distribution beam 2 and a jacking column 4 arranged between the jacking cylinder 3 and the ground. The jacking cylinder 3 and the jacking column 4 are all along the distribution beam 2 There is one column for intervals in the length direction.
[0060] Wherein, the cylinder bottom end surface of the jacking oil cylinder 3 is fixedly connected with the lower end surface...
Embodiment 2
[0073] A bridge jacking construction method is characterized in that: comprising the following construction steps:
[0074] step one:
[0075] 1) Cut the box girder 1 above the bridge along the width direction of the bridge, so that the box girder 1 that needs to be lifted becomes independent;
[0076] 2) Set the partial pressure block 19 formed by concrete prefabrication on the ground;
[0077] Step 2: fixedly install the distribution beam 2 on the lower end surface of the box girder 1, and distribute the distribution beam 2 on both sides of the pier 24;
[0078] Step 3: Set jacking cylinder 3:
[0079] The jacking cylinder 3 is fixed on the lower end surface of the distribution beam 2, the bottom end of the cylinder body of the jacking cylinder 3 is fixed to the lower end surface of the distribution beam 2, and the jacking cylinders 3 are arranged in a row along the length direction of the distribution beam 2 at intervals;
[0080] Step 4: Set the jacking column 4 between...