Abstract
Description
technical field
[0001] The invention relates to the technical field of construction equipment, in particular to equipment and a method for removing pile heads of bridge pile foundations. Background technique
[0002] In the process of bridge construction, the pile foundation needs to be built first. In order to ensure the quality of the pile head during the pile foundation construction, the elevation of the pile top is generally higher than the design elevation. The pile head in the pile foundation construction is made of reinforced concrete. Excess pile foundation pile heads need to be cut off after completion.
[0003] However, the following difficult problems exist in the cutting process of existing pile foundation pile heads, a. Existing pile foundation pile heads need to be cut off manually using a cutting machine, and the positions of concrete and steel bars cannot be accurately judged during the cutting operation. It is easy to cause the circular saw on the cutting m...