Nuclear power plant personnel airlock and installation method thereof
A technology for personnel gates and nuclear power plants, applied in the field of nuclear power plant equipment, can solve problems such as low transmission accuracy, unsatisfactory sealing leakage rate, and inconvenient installation
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0045] The invention provides a nuclear power plant personnel gate, which is suitable for nuclear power plant double-layer containment, such as figure 1 As shown: the double-layer containment vessel includes an outer containment vessel 1 and an inner containment vessel 2, and the inner containment vessel 2 and the outer containment vessel 1 are respectively provided with an inner embedded penetration piece 4 and an outer embedded penetration piece 3, and the personnel gate penetrates the inner The embedded penetration part 4 and the external embedded penetration part 3, the internal embedded penetration part 4 is fixedly connected with the personnel gate; the external embedded penetration part 3 is flexibly and sealingly connected with the personnel gate.
[0046] The personnel gate includes: a cylinder section assembly 5, which penetrates the inner embedded penetration 4 and the outer embedded penetration 3, and is used to support the inner embedded penetration 4 and the outer...
Embodiment 2
[0074] The invention also provides a method for installing personnel gates in nuclear power plants, such as Figure 7 Shown: This installation method includes:
[0075] Step S1: Fix the support bracket to the predetermined overall horizontal introduction installation position of the personnel gate through expansion bolts, and support the support bracket A to the outer containment shell 1 through wooden blocks;
[0076] Step S2. After the support bracket A is connected and fixed, install the first sliding bracket, the second sliding bracket and the transfer trolley on the support bracket A, and adjust the elevation of the transfer trolley by adjusting the shim set. After adjustment, it is fixedly connected by connecting bolts;
[0077] Step S3, hoisting the entire personnel gate in vertically by an off-site crane, and fixing it to the first sliding bracket and the second sliding bracket through a wire rope;
[0078] Step S4, install the tow chain, pull the entire personnel ga...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com