Method for burying monitoring method for monitoring bedrock settlement
A subsidence and monitoring point technology is applied in the field of burying monitoring points for monitoring bedrock subsidence, which can solve the problems of no reserved free section, lack of firmness, affecting the accuracy of subsidence, etc., and achieve the effect of ensuring the accuracy of measurement
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0026] A method for embedding monitoring points for monitoring bedrock settlement, comprising the following steps:
[0027] S1: Drill according to the burial depth of the bedrock, and drill to a depth of 3-5 meters in the micro-weathered layer of the bedrock;
[0028] S2: Clean the bottom of the borehole, and use casing 1 to protect the Quaternary soil above the borehole;
[0029] S3: Bury the pole 2 to the bottom of the borehole, the top of the pole 2 passes through the ground, and anchor the pole 2 placed in the slightly weathered layer in the bedrock;
[0030] S4: Install the pole head at the end of the pole 2 passing through the ground.
[0031] Wherein, before performing step S1, conventional pre-work needs to be carried out, including on-site stakeout and fixed points according to the design drawings, preparation for drilling construction and erection of the drilling rig.
[0032] On-site stakeout to determine the points, details are as follows:
[0033] According to ...
Embodiment 2
[0060] This method can effectively avoid the interference and influence of Quaternary soil, such as figure 2 As shown, it is a comparison table of settlement measurement results of bedrock, brine wells, and corresponding monitoring points on the ground in the Yulonggui Nitrate Mine mining area. This table shows the comparison of the settlement data monitored by the bedrock settlement monitoring points implemented by this method and the settlement data of the mine monitoring, and 3 sets of comparison examples are set to compare the settlement measurement monitoring implemented by this method with the mine settlement monitoring .
[0061] Among them, serial numbers 1, 4, and 8 correspond to monitoring point numbers: base 2, base 3, and base 5 indicate bedrock settlement monitoring points, and serial numbers 2, 5, and 9 correspond to monitoring point numbers: 3-2#, 16* 2#, 12-1# represent mine monitoring points, serial numbers 3, 7, 10, corresponding monitoring point numbers ar...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com