Embodiment 1
[0033] like Figure 1-2 As shown, a grouting-free planting bar structure with an expanding head and its construction method, including tie bars 3, also include embedded tubes 4 and embedded parts 2 that are pre-embedded in reinforced concrete 1 in sequence, and embedded parts The middle part of 2 has a round hole 21, and the round hole 21 communicates with the embedded tube 4 and is located on the same horizontal line. One end of the tie bar 3 is provided with an expanding head 31, and the expanding head 31 can slide in the embedded tube 4 and expand The diameter of the head 31 is larger than the diameter of the circular hole 21 .
[0034] Working principle: While laying reinforced concrete 1, the pre-embedded tube 4 and the embedded parts 2 with round holes 21 are pre-embedded in the reinforced concrete 1 in sequence, and the pre-embedded tube 4 is pre-embedded in the reinforced concrete 1 first, Then extend the enlarged head 31 with the tie bar 3 into the embedded tube 4, a...
Embodiment 2
[0037] like Figure 1-2 As shown, on the basis of the above-mentioned embodiments, this embodiment provides a preferred structure of the embedded part and the embedded cylinder. That is, the embedded part 2 is a pre-embedded slab, and the pre-embedded slab is vertically arranged, and the tie bars 3 are connected to the pre-embedded slab, and the pre-embedded slab is pre-embedded in the reinforced concrete 1, and the contact area between the pre-embedded slab and the reinforced concrete 1 is large. When the tie bars 3 are subjected to horizontal tension or vertical shear force, due to the transferability of the force, the stress area of the tie bars 3 is indirectly increased, so that the masonry structure and reinforced concrete 1 are connected more firmly; the pre-embedded tube 4 is a PVC plastic round pipe, which is durable, and the pre-embedded PVC plastic round pipe can provide a good sliding place for the enlarging head 31.
[0038] Preferably, the outer surface of the ...
Embodiment 3
[0042] like Figure 1-2 As shown, on the basis of Examples 1-2, this example provides a preferred structure that can further increase the firmness of the connection between the masonry structure and the reinforced concrete. That is, the side of the pre-embedded slab is connected with a plurality of anchor bars 5 extending into the reinforced concrete 1, and the tie reinforcement 3 is transmitted to the pre-embedded slab by the tension or shear force of the masonry structure, and the pre-embedded slab then transfers the tensile force to the pre-embedded slab. Or the shearing force is transmitted to the anchoring steel bar 5. Since the anchoring steel bar 5 is embedded in the reinforced concrete 1, the anchoring steel bar 5 can increase the anchoring capacity of the embedded slab, thereby further strengthening the connection between the masonry structure and the reinforced concrete 1. of firmness.
[0043] Preferably, the number of anchoring steel bars 5 on the same cross secti...