A water-cooled wall tube, all-position technology, applied in the direction of welding equipment, auxiliary welding equipment, welding/cutting auxiliary equipment, etc., can solve the problem of welding skills training effect for workers who cannot weld, have a single structure, and cannot simulate the small spacing between water-cooled wall tubes Welding environment and other problems can reduce the risk of boiler "explosion", solve the problem of single position and angle, and improve the qualified rate of welding joints
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0043] When performing welding training, take the working face of the second pipe group as an example, and perform a 45° pipe butt oblique welding position (6G welding position). Such as figure 2 As shown, in the first step, the height adjustment sleeve 4 in the full position adjustment arm 12 is arranged on the column 2, and the position of the height adjustment sleeve 4 is moved up and down according to the height of the welder and the welding angle to determine the best welding position. It is fixed by height adjustment lock nut 3. The cooperation of the height adjustment sleeve 4 and the height adjustment lock nut 3 can not only ensure that welding technicians perform welding work at the optimum height position, but also avoid welding quality problems caused by the up and down displacement of the welding frame during the welding process. In the second step, the fixed platform 18 of the working surface is connected with the full-position adjustment arm 12 via the horizont...
Embodiment 2
[0045] When the pipe fittings to be welded are welded at the vertical position (2G) of the horizontal plane, in the first step, the height adjustment sleeve 4 in the full position adjustment arm 12 is set on the column 2, and the full position is adjusted according to the height of the welder and the welding angle Adjust the height of the arm 12 on the column 2. After determining the proper height of the full position adjustment arm 12, it is fixed by the height adjustment lock nut 3. In the second step, the fixed platform 18 of the working surface is connected with the full-position adjustment arm 12 via the horizontal connection sleeve 10, and the horizontal connection sleeve 10 is connected with the 0° fixing hole 6, and the full-position adjustment arm 12 and the working surface are fixed by the horizontal adjustment bolt 9. Fixed platform 18. The third step is to place one end of the fixed test piece to be welded on the pipe fitting fixing angle iron 16 in the centralize...
Embodiment 3
[0047] When the pipe fittings to be welded are welded at the pipe butt joint horizontal position (5G), in the first step, the height adjustment sleeve 4 in the all-position adjustment arm 12 is set on the column 2, according to the height of the welder and the actual welding position Adjust the height of the full position adjustment arm 12 and the column 2. After determining the proper height of the full position adjustment arm 12, it is fixed by the height adjustment lock nut 3. In the second step, the fixed platform 18 of the working surface is connected with the full-position adjustment arm 12 via the horizontal connection sleeve 10, and the horizontal connection sleeve 10 is connected with the 90° fixing hole 8, and the full-position adjustment arm 12 and the working surface are fixed by the horizontal adjustment bolt 9 Fixed platform 18. The third step is to place one end of the spot-fixed test piece to be welded on the pipe fitting fixing angle iron 16 in the centralize...