A technology of construction engineering and installation method, which is applied in the direction of construction, building components, building structures, etc., can solve the problems of unsatisfactory installation of building partition panels, poor waterproof effect of the bottom of building partition panels, etc., and achieve the construction process layout Reasonable, high construction efficiency, and the effect of improving the installation strength
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0055] Embodiment one, with reference to Figure 1~3 A method for construction and installation of a construction engineering partition board, comprising the steps of:
[0056] S1. Stake out the position of the partition wall; according to the design drawings, carry out a stakeout on the position of the partition wall facing the relevant ground and walls, and mark the positions of the door and window openings at the same time.
[0057] S2, guide wall construction;
[0058] S3, fix the keel along the ground and the frame;
[0059] S4, install the vertical keel;
[0060] S5, install door and window frames;
[0061] S6, plumbing, electrical pipe laying;
[0062] S7, installing gypsum panels;
[0063] S8, caulking;
[0064] Wherein, the specific steps of setting out the position of the partition wall in S1 are as follows:
[0065] S101, floor and wall elastic thread;
[0066] S102, marking the positions of door and window openings;
[0067] Wherein, the specific steps of ...
Embodiment 2
[0073] Embodiment two, refer to Figure 1~4 A method for construction and installation of a construction engineering partition board, comprising the steps of:
[0074] S1. Stake out the position of the partition wall; according to the design drawings, carry out a stakeout on the position of the partition wall facing the relevant ground and walls, and mark the positions of the door and window openings at the same time.
[0075] S2, guide wall construction;
[0076] S3, fix the keel along the ground and the frame;
[0077] S4, install the vertical keel;
[0078] S5, install door and window frames;
[0079] S6, plumbing, electrical pipe laying;
[0080] S7, installing gypsum panels;
[0081] S8, caulking;
[0082] Wherein, the specific steps of setting out the position of the partition wall in S1 are as follows:
[0083] S101, floor and wall elastic thread;
[0084] S102, marking the positions of door and window openings;
[0085] Wherein, the specific steps of the guide w...
Embodiment 3
[0095] Embodiment three, refer to Figure 1~5 A method for construction and installation of a construction engineering partition board, comprising the steps of:
[0096] S1. Stake out the position of the partition wall; according to the design drawings, carry out a stakeout on the position of the partition wall facing the relevant ground and walls, and mark the positions of the door and window openings at the same time.
[0097] S2, guide wall construction;
[0098] S3, fix the keel along the ground and the frame;
[0099] S4, install the vertical keel;
[0100] S5, install door and window frames;
[0101] S6, plumbing, electrical pipe laying;
[0102] S7, installing gypsum panels;
[0103] S8, caulking;
[0104] Wherein, the specific steps of setting out the position of the partition wall in S1 are as follows:
[0105] S101, floor and wall elastic thread;
[0106] S102. Mark the positions of the door and window openings.
[0107] Wherein, the specific steps of the gu...