Flare boom prefabrication, trial-assembly and shipment process
A torch arm and trial installation technology, which is applied in the field of offshore oil engineering, can solve the problems of high construction risk, long crane occupation time, and many high-altitude operations, and achieves the effects of convenient construction, shortened hoisting time, and saved construction period.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0029] The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments, so that those skilled in the art can better understand the present invention and implement it, but the examples given are not intended to limit the present invention.
[0030] Such as figure 1 ~ Figure 9 Shown, the present invention adopts following steps:
[0031] Step 1: Torch Boom 1 is constructed laterally, and auxiliary structures such as the torch boom inclined ladder 2 are prefabricated and installed at low levels. Otherwise, auxiliary structures such as the inclined ladder 2 need to be built at a high level, and a large number of scaffolds will be erected, and the staff will need to work at heights, with a high risk factor.
[0032] Step 2: Hoist the torch arm 1 and turn it over 90 degrees to meet the trial installation conditions.
[0033] This step includes specific steps as follows:
[0034] 1. Three cranes are initially stationed...