NACA (National Advisory Committee for Aeronautics) type water injection device used for scouring prevention of bridge pier tandem pile foundation, and construction method thereof
An anti-scour, pile foundation technology, applied in protection devices, infrastructure engineering, construction, etc., can solve problems such as the impact of bridge safety and stability, the impact on bridge safety and stability, and the decline of pile foundation bearing capacity, so as to improve the bearing capacity. The effect of high strength, simple and fast construction and low cost
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0028] This embodiment discloses a NACA-type water injection device for the anti-scouring of bridge pier serial pile foundations, including a NACA airfoil structure 1 and a number of fixed piles 2, the NACA airfoil structure 1 is made of high-strength plastic, and the NACA airfoil structure 1 The outer wall of the airfoil is NACA airfoil surface.
[0029] see image 3 , the NACA airfoil structure 1 is provided with pile foundation penetration holes 101 through which several fixed piles 2 and pile foundations 3 pass, and the pile foundation penetration holes 101 run through the upper and lower surfaces of the NACA airfoil structure 1 .
[0030] see figure 1 Or 3, there is a cavity S between the hole wall of the pile foundation penetration hole 101 and the outer surface of the NACA airfoil structure 1, and the upper surface of the NACA airfoil structure 1 is provided with two reserved holes 102, sand or gravel Concrete mortar is injected into the cavity S through the reserved ...
Embodiment 2
[0037] Based on the device described in Embodiment 1, this embodiment discloses a construction method for an anti-scouring NACA type water injection device for pier tandem pile foundations, including the following steps:
[0038] 1) The NACA airfoil structure 1 and some fixed piles 2 are produced according to the actual size of the tandem pile foundation in the project.
[0039] 2) On the horizontal plane, untie the mortise and tenon structure 4, and the pile foundation penetration hole 101 forms a gap in the vertical direction, through which the NACA airfoil structure 1 is set on several serial pile foundations 3, and then Fasten the mortise and tenon structure 4. Wherein, the pile foundations 3 at both ends are in close contact with the inner sidewall of the NACA airfoil structure 1 .
[0040] 3) Sandstone or concrete mortar is injected into the cavity S through the two reserved holes 102, and the NACA airfoil structure 1 sinks to the upper surface of the foundation soil la...
Embodiment 3
[0043]This embodiment discloses a NACA-type water injection device for anti-scouring of tandem pile foundations of bridge piers, which includes a NACA airfoil structure 1 and several fixed piles 2, and the outer wall of the NACA airfoil structure 1 is a NACA airfoil curved surface.
[0044] see image 3 , the NACA airfoil structure 1 is provided with pile foundation penetration holes 101 through which several fixed piles 2 and pile foundations 3 pass, and the pile foundation penetration holes 101 run through the upper and lower surfaces of the NACA airfoil structure 1 .
[0045] There is a cavity S between the inner wall and the outer wall of the NACA airfoil structure 1, and the upper surface of the NACA airfoil structure 1 is provided with two reserved holes 102, and sand or concrete mortar is injected into the cavity through the reserved holes 102 Inside S.
[0046] see figure 1 Or 2, the upper surface of the NACA airfoil structure 1 is flush with the horizontal plane, th...