Optimization calculation method for mountainous road earthwork volume

A technology for optimizing calculation and earthwork, applied in calculation, design optimization/simulation, image data processing and other directions, can solve the problems of large error, low efficiency, high measurement cost, improve scientificity and accuracy, improve calculation efficiency, The effect of reducing the computational workload

Pending Publication Date: 2020-10-16
CHINA MCC20 GRP CORP
View PDF3 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

This method of obtaining data is increasingly unsuitable for the shortage of professional and technical personnel such as measurement in my country, and requires a lot of manpower and material costs. The measurement cost is too high, the efficiency is low, and the error is large.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Optimization calculation method for mountainous road earthwork volume
  • Optimization calculation method for mountainous road earthwork volume
  • Optimization calculation method for mountainous road earthwork volume

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0032] Example figure 1 Shown, the optimal calculation method of mountain road earthwork quantity of the present invention comprises the steps:

[0033] Step 1. Collecting and arranging geographical location data, initial topographical data and road construction drawings of roads in mountainous areas;

[0034] Step 2. Obtain the terrain elevation data of the road construction area through the BIM road design system, identify elevation points or contour lines, and establish the initial terrain surface 1 of the mountainous road;

[0035] Step 3: Establish a mountainous road model on the initial terrain surface 1 according to the road construction drawing, and generate an initial subgrade cross-sectional view;

[0036] Step 4. Carry out mountainous road construction according to the road construction drawing, measure the scope of the construction area after construction, and obtain the elevation data of the construction area after construction;

[0037] Step 5. Replace the elev...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses an optimization calculation method for mountainous area road earthwork volume. The method comprises the following steps: acquiring road elevation data, establishing a road initial terrain curved surface, generating an initial roadbed cross section diagram, acquiring construction area elevation data after road construction, replacing the elevation data of the initial terraincurved surface, and establishing a constructed terrain curved surface; replacing the initial topographic curved surface with a constructed topographic curved surface to generate a constructed roadbedcross section diagram; forming a roadbed cross section comparison diagram according to the same pile number, performing earthwork amount calculation according to different pile intervals, fitting according to the relation between the pile intervals and excavation and fill errors and a linear function, and obtaining the maximum linear pile interval, meeting the maximum error requirement, of the excavation and fill amount; calculating the cross section area of the road earthwork and the excavation area of the excavation and fill retaining wall; and calculating the excavated earth volume according to the area and the distance, and adding the excavated volume of the excavated and filled retaining wall to obtain the excavated and filled earth volume of the mountainous road. The method improvesthe scientificity and accuracy of calculation.

Description

technical field [0001] The invention relates to the technical field of road engineering, in particular to an optimal calculation method for earthwork volume of roads in mountainous areas. Background technique [0002] Due to the large ups and downs of the roads in mountainous areas, a large amount of excavation and filling will be generated during road construction, especially for high slope sections, the amount of excavation and filling will be even greater. The earthwork volume of mountainous roads is an important part of the investment and settlement of road engineering construction. Accurately calculating the earthwork volume of mountainous roads is of great significance to the budget in the early stage of the project and the settlement in the later stage. However, the calculation method of excavation and filling volume, the reasonable calculation range of excavation and filling volume, and the calculation accuracy have a great influence on the accuracy of the calculatio...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): G06F30/13G06F30/20G06T17/05
CPCG06F30/13G06F30/20G06T17/05
Inventor 徐宁杨华杰李印冬赵建立张天福
Owner CHINA MCC20 GRP CORP